shpslogo.jpg (6992 bytes)

Contact Us - Tell A Friend - Make a Donation - Free-Ed.Net Home

MIXING CONCRETE

LEARNING OBJECTIVE:

Upon completing this section, you should be able to determine methods and mixing times of concrete.

Concrete is mixed either by hand or machine. No matter which method is used, you must follow well-established procedures if you expect finished concrete of good quality. An oversight in proper concrete mixing, whether through lack of competence or inattention to detail, cannot be corrected later.

MIXING BY HAND

A batch to be hand mixed by a couple of crewmembers should not be much larger than 1 cubic yard. The equipment required consists of a watertight metal or wooden platform, two shovels, a metal-lined measuring box, and a graduated bucket for measuring the water.

The mixing platform does not need to be made of expensive materials. It can be an abandoned concrete slab or concrete parking lot that can be cleaned after use. A wooden platform having tight joints to prevent the loss of paste may be used. Whichever surface is used, you should ensure that it is cleaned prior to use and level.

Let’s say your batch consists of two bags of cement, 5.5 cubic feet of sand, and 6.4 cubic feet of coarse aggregate. Mix the sand and cement together first, using the following procedure:

  1. Dump 3 cubic feet of sand on the platform first, spread it out in a layer, and dump a bag of cement over it.
  2. Spread out the cement and dump the rest of the sand (2.5 cubic feet) over it.
  3. Dump the second sack of cement on top of the lot.

This use of alternate layers of sand and cement reduces the amount of shoveling required for complete mixing.

Personnel doing the mixing should face each other from opposite sides of the pile and work from the outside to the center. They should turn the mixture as many times as is necessary to produce a uniform color throughout. When the cement and sand are completely mixed, the pile should be leveled off and the coarse material added and mixed by the same turning method.

The pile should next be troughed in the center. The mixing water, after being carefully measured, should be poured into the trough. The dry materials should then be turned into the water, with great care taken to ensure that none of the water escapes. When all the water has been absorbed, the mixing should continue until the mix is of a uniform consistency. Four complete turnings are usually required.

MIXING BY MACHINE

The size of a concrete mixer is designated by its rated capacity. As we mentioned earlier, the capacity is expressed in terms of the volume of mixed concrete, not of dry ingredients the machine can mix in a single batch. Rated capacities run from as small as 2 cubic feet to as large as 7 cubic yards (189 cubic feet).

fig0506.jpg (14748 bytes)

Figure 6-6.-Model 16-S concrete mixer.

The production capacity of the 16-S mixer varies between 5 and 10 cubic yards per hour, depending on the efficiency of the personnel. Aggregate larger than 3 inches will damage the mixer. The mixer consists of a frame equipped with wheels and towing tongue (for easy movement), an engine, a power loader skip, mixing drum, water tank, and an auxiliary water pump. The mixer may be used as a central mixing plant.

Charging the Mixer

Concrete mixers may be charged by hand or with the mechanical skip. Before loading the mechanical skip, remove the towing tongue. Then cement, sand, and gravel are loaded and dumped into the mixer together while the water runs into the mixing drum on the side opposite the skip. A storage tank on top of the mixer measures the mixing water into the drum a few seconds before the skip dumps. This discharge also washes down the mixer between batches. The coarse aggregate is placed in the skip first, the cement next, and the sand is placed on top to prevent excessive loss of cement as the batch enters the mixer.

Mixing Time

It takes a mixing machine having a capacity of 27 cubic feet or larger 1 1/2 minutes to mix a 1-cubic yard batch. Another 15 seconds should be allowed for each additional 1/2 cubic yard or fraction thereof. The water should be started into the drum a few seconds before the skip begins to dump, so that the inside of the drum gets a washout before the batched ingredients go in. The mixing period should be measured from the time all the batched ingredients are in, provided that all the water is in before one-fourth of the mixing time has elapsed. The time elapsing between the introduction of the mixing water to the cement and aggregates and the placing of the concrete in the forms should not exceed 1 1/2 hours.

Discharging the Mixer

When the material is ready for discharge from the mixer, the discharge chute is moved into place to receive the concrete from the drum of the mixer. In some cases, stiff concrete has a tendency to carry up to the top of the drum and not drop down in time to be deposited on the chute. Very wet concrete may not carry up high enough to be caught by the chute. This condition can be corrected by adjusting the speed of the mixer. For very wet concrete, the speed of the drum should be increased. For stiff concrete, the drum speed should be slowed down,

Cleaning and Maintaining the Mixer

The mixer should be cleaned daily when it is in continuous operation or following each period of use if it is in operation less than a day. If the outside of the mixer is kept coated with oil, the cleaning process can be speeded up. The outside of the mixer should be washed with a hose, and all accumulated concrete should be knocked off. If the blades of the mixer become worn or coated with hardened concrete, the mixing action will be less efficient. Badly worn blades should be replaced. Hardened concrete should not be allowed to accumulate in the mixer drum. The mixer drum must be cleaned out whenever it is necessary to shut down for more than 1 1/2 hours. Place a volume of coarse aggregate in the drum equal to one-half of the capacity of the mixer and allow it to revolve for about 5 minutes. Discharge the aggregate and flush out the drum with water. Do not pound the discharge chute, drum shell, or the skip to remove aggregate or hardened concrete. Concrete will readily adhere to the dents and bumps created. For complete instructions on the operation, adjustment, and maintenance of the mixer, study the manufacturer’s manual.

All gears, chains, and rollers of mixers should be properly guarded. All moving parts should be cleaned and properly serviced to permit safe performance of the equipment. When the mixer drum is being cleaned, the switches must be open, the throttles closed, and the control mechanism locked in the OFF position. The area around the mixer must be kept clear.

Skip loader cables and brakes must be inspected frequently to prevent injuries caused by falling skips. When work under an elevated skip is unavoidable, you must shore up the skip to prevent it from falling in the event that the brake fails or is accidentally released. The mixer operator must never lower the skip without first making sure that there is no one underneath.

Dust protection equipment must be issued to the crew engaged in handling cement, and the crew must wear the equipment when so engaged. Crewmembers should stand with their backs to the wind, whenever possible. This helps prevent cement and sand from being blown into their eyes and faces.

HANDLING AND TRANSPORTING CONCRETE

When ready-mixed concrete is carried by an ordinary type of carrier (such as a wheelbarrow or buggy), jolting of the carrier increases the natural tendency of the concrete to segregate. Carriers should therefore be equipped with pneumatic tires whenever possible, and the surface over which they travel should be as smooth as possible.

A long free fall also causes concrete to segregate. If the concrete must be discharged at a level more than 4 feet above the level of placement, it should be dumped into an "elephant trunk" similar to the one shown in figure 6-7.

fig0507.jpg (29162 bytes)

Figure 6-7.-Chute, or downpipe used to check free fall of concrete.

Segregation also occurs when discharged concrete is allowed to glance off a surface, such as the side of a form or chute. Wheelbarrows, buggies, and conveyors should discharge so that the concrete falls clear.

Concrete should be transported by chute only for short distances. It tends to segregate and dry out when handled in this manner. For a mix of average workability y, the best slope for a chute is about 1 foot of rise to 2 or 3 feet of run. A steeper slope causes segregation, whereas a flatter slope causes the concrete to run slowly or not at all. The stiffer the mix, the steeper the slope required. All chutes and spouting used in concrete pours should be clean and well-supported by proper bracing and guys.

When spouting and chutes run overhead, the area beneath must be cleared and barricaded during placing. This eliminates the concrete or possible collapse.

READY-MIXED CONCRETE

On some jobs, such as large danger of falling highway jobs, it is possible to use a batch plant that contains its own mixer. A plant of this type discharges ready-mixed concrete into transit mixers, which haul it to the construction site. The truck carries the mix in a revolving chamber much like the one on a mixer. Keeping the mix agitated in route prevents segregation of aggregate particles. A ready-mix plant is usually portable so that it can follow the job along. It must be certain, of course, that a truck will be able to deliver the mix at the site before it starts to set. Discharge of the concrete from the drum should be completed within 1 1/2 hours.

TRANSIT-MIXED CONCRETE

By transit-mixing, we refer to concrete that is mixed, either wet or dry, en route to a job site. A transit-mix truck carries a mixer and a water tank from which the driver can, at the proper time, introduce the required amount of water into the mix. The truck picks up the dry ingredients at the batch plant, together with a slip which tells how much water is to be introduced to the mix upon arrival at the site. The mixer drum is kept revolving in route and at the job site so that the dry ingredients do not segregate. Transit-mix trucks are part of the battalion’s equipment inventory and are widely used on all but the smallest concrete jobs assigned to a battalion.

PRECAST AND TILT-UP CONCRETE

LEARNING OBJECTIVE:

Upon completing this section, you should be able to determine projects suitable for and lifting methods necessary for precast and tilt-up construction.

Concrete cast in the position it is to occupy in the finished structure is called cast-in-place concrete. Concrete cast and cured elsewhere is called precast concrete. Tilt-up concrete is a special type of precast concrete in which the units are tilted up and placed using cranes or other types of lifting devices.

Wall construction, for example, is frequently done with precast wall panels originally cast horizontally (sometimes one above the other) as slabs. This method has many advantages over the conventional method of casting in place in vertical wall forms. Since a slab form requires only edge forms and a single surface form, the amount of formwork and form materials required is greatly reduced. The labor involved in slab form concrete casting is much less than that involved in filling a high wall form. One side of a precast unit cast as a slab maybe finished by hand to any desired quality of finishing. The placement of reinforcing steel is much easier in slab forms, and it is easier to attain thorough filling and vibrating. Precasting of wall panels as slabs may be expedited by mass production methods not available when casting in place. Relatively light panels for concrete walls are precast as slabs (figure 6-8). The panels are set in place by cranes, using spreader bars (figure 6-9). Figure 6-10 shows erected panels in final position

fig0508.jpg (21081 bytes)

Figure 6-8.-Precast wall panels in stacks of three each.

 

fig0509.jpg (27411 bytes)

Figure 6-9.-Precast panels being erected by use of crane and spreader bars.

CASTING

The casting surface is very important in making with precast concrete panels. In this section, we will cover two common types: earth and concrete. Regardless of which method you use, however, a slab must be cast in a location that will permit easy removal and handling.

Castings can be made directly on the ground cement poured into forms. These "earth" surfaces are economical but only last for a couple of concrete pours. Concrete surfaces, since they can be reused repeatedly, are more practical.

When building casting surfaces, you should keep the following points in mind:

  • The subbase should be level and properly compacted.
  • The slab should be at least 6 inches thick and made of 3,000 psi or higher reinforced concrete. Large aggregate, 2 1/2 inches to 3 inches maximum, may be used in the casting slabs.
  • If pipes or other utilities are to be extended up through the casting slab at a later date, they should be stopped below the surface and the openings temporarily closed. For wood, cork, or plastic plugs, fill almost to the surface with sand and top with a thin coat of mortar that is finished flush with the casting surface.
  • It is important to remember that any imperfections in the surface of the casting slab will show up on the cast panels. When finishing the casting slab, you must ensure there is a flat, level, and smooth surface without humps, dips, cracks, or gouges. If possible, cure the casting surface keeping it covered with water (pending). However, if a curing compound or surface hardener is used, make sure it will not conflict with the later use of bond-breaking agents.

FORMS

The material most commonly used for edge forms is 2-by lumber. The lumber must be occasionally replaced, but the steel or aluminum angles and charnels may be reused many times. The tops of the forms must be in the same plane so that they maybe used for screeds. They must also be well braced to remain in good alignment.

Edge forms should have holes in them for rebar or for expansion/contraction dowels to protrude. These holes should be 1/4 inch larger in diameter than the bars. At times, the forms are spliced at the line of these bars to make removal easier.

The forms, or rough bucks, for doors, windows, air-conditioning ducts, and so forth, are set before the steel is placed and should be on the same plane as the edge forms.

BOND-BREAKING AGENTS

Bond-breaking agents are one of the most important items of precast concrete construction. The most important requirement is that they must break the bond between the casting surface and the cast panel. Bond-breaking agents must also be economical, fast drying, easily applied, easily removed, or leave a paintable surface on the cast panel, if desired. They are broken into two general types: sheet materials and liquids.

There are many commercially available bond-breaking agents available. You should obtain the type best suited for the project and follow the manufacturer’s application instructions. If commercial bond-breaking agents are not available, several alternatives can be used.

  • Paper and felt effectively prevent a bond with a casting surface, but usually stick to the cast panels and may cause asphalt stains on the concrete.
  • When oiled, plywood, fiberboard, and metal effectively prevent a bond and can be used many times. The initial cost, however, is high and joint marks are left on the cast panels.
  • Canvas gives a very pleasing texture and is used where cast panels are lifted at an early stage. It should be either dusted with cement or sprinkled with water just before placing the concrete.
  • Oil gives good results when properly used, but is expensive. The casting slab must be dry when the oil is applied, and the oil must be allowed to absorb before the concrete is placed. Oil should not be used if the surface is to be painted, and crankcase oil should never be used.
  • Waxes, such as spirit wax (paraffin) and ordinary floor wax, give good-to-excellent results. One mixture that may be used is 5 pounds of paraffin mixed with 1 1/2 gallons of light oil or kerosene. The oil must be heated to dissolve the paraffin.
  • Liquid soap requires special care to ensure that an excess amount is not used or the surface of the cast panel will be sandy.

Materials should be applied after the side forms are in place and the casting slab is clean but before any reinforcing steel is placed. To ensure proper adhesion of the concrete, keep all bond-breaking materials off the reinforcing steel.

REINFORCEMENTS AND INSERTS

Reinforcing bars (rebar) should be assembled into mats and placed into the forms as a unit. This allows for rapid assembly on a jig and reduces walking on the casting surface, which has been treated with the bond-breating agent.

Extra rebars must be used at openings. They should be placed parallel to and about 2 inches from the sides of openings or placed diagonally across the corners of openings.

The bars may be suspended by conventional methods, such as with high chairs or from members laid across the edge forms. However, high chairs should not be used if the bottom of the cast panel is to be a finished surface. Another method is to first place half the thickness of concrete, place the rebar mat, and then complete the pour. However, this method must be done quickly to avoid a cold joint between the top and bottom layers.

When welded wire fabric (WWF) is used, dowels or bars must still be used between the panels and columns. WWF is usually placed in sheets covering the entire area and then clipped along the edges of the openings after erection.

If utilities are going to be flush-mounted or hidden, pipe, conduit, boxes, sleeves, and so forth should be put into the forms at the same time as the reinforcing steel. If the utilities pass from one cast panel to another, the connections must be made after the panels are erected but before the columns are poured. If small openings are to go through the panel, a greased pipe sleeve is the easiest method of placing an opening in the form. For larger openings, such as air-conditioning ducts, forms should be made in the same reamer as doors or windows.

After rebar and utilities have been placed, all other inserts should be placed. These will include lifting and bracing inserts, anchor bolts, welding plates, and so forth. You need to make sure these items are firmly secured so they won’t move during concrete placement or finishing.

POURING, FINISHING, AND CURING

With few exceptions, pouring cast panels can be done in the same manner as other pours. Since the panels are poured in a horizontal position, a stiffer mix can be used. A minimum of six sacks of cement per cubic yard with a maximum of 6 gallons of water per sack of cement should be used along with well-graded aggregate. As pointed out earlier, though, you will have to reduce the amount of water used per sack of cement to allow for the free water in the sand. Large aggregate, up to 1 1/2 inches in diameter, may be used effectively. The concrete should be worked into place by spading or vibration, and extra care must be taken to prevent honeycomb around outer edges of the panel.

Normal finishing methods should be used, but many finishing styles are available for horizontally cast panels. Some finishing methods include patterned, colored, exposed aggregate, broomed, floated, or steel-troweled. Regardless of the finish used, finishers must be cautioned to do the finishing of all panels in a uniform manner. Spots, defects, uneven brooming, or troweling, and so forth will be highly visible when the panels are erected.

Without marring the surface, curing should be started as soon as possible after finishing. Proper curing is important, so cast panels should be cured just like any other concrete to achieve proper strength. Curing compound, if used, prevents bonding with other concrete or paint.

LIFTING EQUIPMENT AND ATTACHMENTS

Tilt-up panels can be set up in many different ways and with various kinds of power equipment. The choice depends upon the size of the job. Besides the equipment, a number of attachments are used.

Equipment

The most popular power equipment is a crane. But other equipment used includes a winch and an A frame, used either on the ground or mounted on a truck. When a considerable number of panels are ready for tilting at one time, power equipment speeds up the job.

Attachments

Many types of lifting attachments are used to lift tilt-up panels. Some of these attachments are locally made and are called hairpins; other types are available commercially. Hairpin types are made on the job site from rebar. These are made by making 180° bends in the ends of two vertical reinforcing bars. The hairpins are then placed in the end of the panel before the concrete is poured. These lifting attachments must protrude from the top of the form for attaching the lifting chains or cables, but go deep enough in the panel form so they won’t pull out.

Among the commercial types of lifting attachments, you will find many styles with greater lifting capacities that are more dependable than hairpins if properly installed. These are used with lifting plates. For proper placement of lifting inserts, refer to the plans or specs.

Spreader Bars

Spreader bars (shown in figure 6-9) may be permanent or adjustable, but must be designed and made according to the heaviest load they will carry plus a safety factor. They are used to distribute the lifting stresses evenly, reduce the lateral force applied by slings, and reduce the tendency of panels to bow.

POINT PICKUP METHODS

Once the concrete has reached the desired strength, the panels are ready to be lifted. The strength of the inserts is governed by the strength of the concrete.

CAUTION

An early lift may result in cracking the panel, pulling out the insert, or total concrete failure. The time taken to wait until the concrete has reached its full strength prevents problems and minimizes the risk of injury.

There are several different pickup methods. The following are just some of the basics. Before using these methods on a job, make sure that you check plans and specs to see if these are stated there. Figure 6-11 shows four different pickup methods: 2, 2-2, 4-4, and 2-2-2.

The 2-point pickup is the simplest method, particularly for smaller panels. The pickup cables or chains are fastened directly from the crane hook or spreader bar to two pickup points on or near the top of the precast panel.

The 2-2 point pickup is a better method and is more commonly used. Variations of the 2-2 are 4-4 and 2-2-2, or combinations of pickup points as designated in the job site specifications. These methods use a combination of spreader bars, sheaves, and equal-length cables. The main purpose is to distribute the lifting stresses throughout the panel during erection. Remember, the cables must be long enough to allow ample clearance between the top of the panel and the sheaves or spreader bar.

 

ERECTING, BRACING, AND JOINTING PANELS

Erecting is an important step in the construction phase of the project. Before you start the erecting phase and for increased safety, you should make sure that all your tools, equipment, and braces are in proper working order. All personnel must be well informed and the signalman and crane operator understand and agree on the signals to be used. During the erection of the panels, make sure that the signalman and line handler are not under the panel and that all unnecessary personnel and equipment are away from the lifting area. After the erection is done, make sure that all panels are properly braced and secured before unhooking the lifting cables.

fig0510.jpg (81919 bytes)

Figure 6-10.-Precast panels in position.

Bracing is an especially important step. After all the work of casting and placing the panels, you want them to stay in place. The following are some steps to take before lifting the panels:

  • Install the brace inserts into the panels during casting if possible.
  • Install the brace inserts into the floor slab either during pouring or the day before erection.
  • Install solid brace anchors before the day of erection.
  • If brace anchors must be set during erection, use a method that is fast and accurate.

Although there are several types of bracing, pipe or tubular braces are the most common. They usually have a turnbuckle welded between sections for adjustment. Some braces are also made with telescoping sleeves for greater adaptability. Figure 6-10 shows tube-type braces used to hold up panels. Cable braces are normally used for temporary bracing and for very tall panels. Their flexibility and tendency to stretch, however, make them unsuitable for most projects. Wood bracing is seldom used except for low, small panels or for temporary bracing,

Jointing the panels is simple. Just tie all the panels together, covering the gap between them. You can weld, bolt, or pour concrete columns or beams. Steps used to tie the panels should be stated in the plans and specs.

fig0511a.jpg (56597 bytes)

 

fig0511b.jpg (91989 bytes)

fig0511d.jpg (102167 bytes)
fig0511c.jpg (121393 bytes) fig0511e.jpg (83537 bytes)

 

Primary Content Provider: U.S. Army
Editor and Publisher: David L. Heiserman, SweetHaven Publishing Services

Copyright © 2007, SweeetHaven Publishing Services
All Rights Reserved