Lesson 8
Light
Floor and Wall Framing
In the normal sequence of construction events, the floor and
wall activities follow the completed foundation work. In this chapter, well examine
established methods of frame construction and discuss in general how floor and wall
framing members are assembled. An explanation of subflooring installation, exterior
sheathing, interior partitions, and rough openings for doors and windows is also given.
8-1
Wood Sill Framing
8-2
Floor Framing
8-3
Wall Framing
8-4
Ceiling Framing

|