The leveling operation is used to determine the elevations of points or the differences in elevation between points on the earth�s surface. The leveling operation is important for deriving the data required for various engineering designs, mapping, and construction projects. Data from a finished level survey is used to design roads, highways, and airfields. The data is also used to develop maps showing the general configuration of the ground. Information obtained from leveling operations is used to calculate the volume of earthwork required to complete a construction project.
This lesson addresses the basic principles of direct leveling and the methods used, as well as the duties and responsibilities of the leveling crew. Differential leveling field procedures, precision leveling, and the proper handling of leveling instruments and equipment are also discussed. In addition, this lesson includes a general description of basic engineering surveys and various construction site safety hazards commonly encountered by a survey party.
When you have completed this lesson, you will be able to:
| 1.0.0 Basic Terms Used in Leveling Operations
2.0.0 Level Party Organization, Equipment, and Field Procedures 3.0.0 Methods of Leveling 4.0.0 Precision in Leveling; Mistakes and Errors in Leveling 5.0.0 Basic Engineering Surveys and Construction Site Safety |
Direct leveling describes the method of measuring vertical distances (differences in elevation) between the plane of known or assumed elevation (datum) and the plane of a point whose elevation is being sought. After the distances are known, they may be added to or subtracted from the known or assumed elevation to get the elevation of the desired point. These vertical distances are measured by using a leveling rod and, usually, an engineer�s level.
Basic vertical control for topographic survey and mapping is derived from first- and second-order leveling. For many construction projects and for filling gaps between second-order bench marks (BMs), less precise third-order leveling is acceptable.
In leveling, a level reference surface, or datum, is established, and an elevation is assigned. This datum may be assigned an assumed elevation, but true elevation is required for the establishment of a BM. A series of properly established BMs is therefore the framework of any vertical control.
Some of the basic terms commonly used in leveling operations are defined in the following paragraphs.
A bench mark is a relatively permanent object, natural or artificial, bearing a marked point whose elevation is known. BMs are established over an area to serve as the following:
BMs are classified as permanent or temporary. Temporary bench marks (TBMs) are established and retained for the duration of a particular job. Permanent bench marks are established by various governmental agencies. These identification markers are set in stone, iron pipe, or concrete and are sometimes marked with the elevation above sea level. Typical markers are shown in Figure 15-1.
Figure 15-1 � Survey markers.
When an elevation is not marked, the information can be found by contacting the governmental agency responsible for the original BM.
BMs may be constructed in several ways. Figure 15-2 shows brass shaft stocks in the tops of permanent horizontal control points (monuments). Monuments of this type may also be used as vertical control BMs. Original BMs may be constructed in the same manner.
Figure 15-2 � Horizontal control markers used as BMs.
For short lines and a level circuit of a limited area, any substantial object may be used for vertical control BMs. A remark in your field notes should detail the proper identification of the BMs used.
Figure 15-3 shows a mark commonly used on tops of concrete walls and foundations. Lines are chiseled with a cold chisel or small star drill and then marked with paint or keel (lumber crayon). The chiseled figures should be about the same size as the base area of the rod, preferably, placed on some high spot on the surface of the concrete structure.
Figure 15-3 � Benchmarks located on concrete structure.
A spike may be driven into the root of a tree or placed higher up on the trunk of the tree when the limb clearance allows higher rod readings, as shown in Figure 15-4. The rod should be held on the highest edge of the spike, and the elevation should be marked on the blazed portion of the tree.
Figure 15-4 � Bench mark on tree.
Figure 15-5 shows a spike driven on a pole or post that also represents a BM. The spike has been driven in horizontally on the face of the post in line with the direction of the level line. In order to use this mark, hold the rod on the uppermost edge of the spike. After you calculate the elevation, mark it on the pole or post for future reference.
Figure 15-5 � Bench mark on pole or post.
Stakes driven into the ground can also be used as TBMs, especially if no frost is expected before they are needed.
Monument BMs are often established in a grid system approximately one-half mile apart throughout the base. These BMs, which are generally fenced to mark their location, provide ready referencing elevations for future construction on the station. The fencing also serves to protect the BMs from being accidentally disturbed.
BM systems, or level nets, consist of a series of BMs established within a prescribed order of accuracy along closed circuits. These nets are also tied to a datum. The nets are adjusted by computations that minimize the effects of accidental errors and are identified as being of a specific order of accuracy.
In certain areas, Tidal Bench Marks must be established to obtain the starting datum plane or to check previously established elevations. Tidal bench marks are permanent BMs set on high ground and are tied to the tide station near the water surface.
Tide stations are classified as primary and secondary. Primary stations require observations for periods of 19 years or more to derive basic tidal data for a locality. Secondary stations are operated over a limited period (usually less than 1 year) for a specific purpose, such as checking elevations. Secondary station observations are always compared to and computed from data obtained by primary stations.
A tide station is set up, and observations are made for a period that is determined by a desired accuracy. The observations are then compared with a primary tide station in the area.
A closed loop using spirit levels is run from the tide station over the tidal BMs and is tied back to the tide station. The accuracy of this level line must be the same as or higher than the accuracy required for the BMs.
For permanency, tidal BMs are usually established in sets of three away from the shoreline where natural activity or future construction will not disturb or destroy them.
Tidal datums are specific tide levels used as surfaces of reference for depth measurements in the sea and as a base for determining elevations on land. In leveling operations, the tidal datum most commonly used is the Mean Sea Level. Other datums, such as mean low water, mean lower low water, mean high water, and mean higher high water, are sometimes used, depending upon the purpose of the survey. Still other datums are used in foreign countries. Because of the different datums used in foreign countries, it is important to check datum information when conducting leveling operations overseas.
Mean sea level (MSL) is defined as the average height of the sea for all stages of the tide after long periods of observations. It is calculated by averaging the hourly sea level height. Figure 15-6 shows the heights tabulated on a form.
Figure 15-6 � Hourly heights of tide required for computing average MSL.
The heights on the form are added both horizontally and vertically. The total sum covering 7 days is entered in the lower right-hand corner of the page. The mean for each calendar month is calculated by combining all daily sums for the month and dividing by the total number of hours in the month. The monthly mean, to two decimal places, is entered on the sheet that includes the record for the last day of the month. Yearly means are determined from the monthly means, and a mean is taken of all yearly means for the period of record. Three or more years of record should be used to determine a reliable sea level. The actual value varies from place to place, but the variation is small. The station used to determine MSL should be on the open coast or on the shore of bays or harbors having free access to the sea. Stations on tidal rivers some distance from the open sea will have a Mean River Level that is higher than mean sea level because of the river slope. It should be noted that MSL is not identical with mean tide level (MTL). MTL is derived from the mean of all high and low points on the tidal curve.
Along the Atlantic coast of the United States, the mean low water (MLW) datum has been adopted as the datum used for hydrographic surveys. It is the mean of all low water tides observed over a long period (usually a 19-year period). Mean lower low water (MLLW) has been generally adopted for hydrographic surveys along the Pacific coast of the United States, Hawaii, Alaska, and the Philippine Islands. It is the mean of the lower of the two low water tides for each day observed over a long period. Mean low water spring (MLWS) is used on the Pacific coast of the Panama Canal Zone. It is defined as the mean of the low waters of the spring tides occurring a day or two after a full moon and is calculated by subtracting one-half of the range of the spring tides from the mean sea tide level.
| Test Your Knowledge 1. Bench marks (BMs) share what common characteristic?
2. Level nets are established within a prescribed order of accuracy and are tied to what reference?
3. What datum is generally used for measuring the height of a hill?
|
Basic preparations must be performed before any leveling survey is conducted. Proper planning and thorough identification of the procedures are essential to the success of the leveling operation. Participating in preparatory work enhances the experience and increases the capabilities of the crew members. Some of the preparatory work is discussed in the following paragraphs.
The size of the leveling party is dependent upon such variables as the order of accuracy required and the number of experienced personnel available. Ordinarily, the smallest crew consists of two individuals: an instrumentman and a rodman. To improve the efficiency of the leveling operations, additional personnel are required. The addition of a second rodman to alternate on backsights (BSs) and foresights (FSs) speeds up the leveling operation. By adding a recorder, the instrumentman can take readings as soon as the rodmen are in position. In surveys requiring a shaded instrument, an umbrellaman is required.
An instrumentman, or levelman, runs the level and makes adjustments required for proper operation. The instrumentman ensures no stations are omitted, turning points (TPs) are properly selected, and BMs are properly established and identified. The instrumentman is usually designated by the engineering tech1 or engineering techC to act as the chief of the party. When a two-man leveling party uses a self-reading rod, the instrumentman is also the recorder. However, if a target rod is used, the rodman usually acts as the recorder. A good instrumentman keeps within the required limits of error.
The chief of the party must be alert to recognize common problems encountered in the field and be able and ready to solve them using the best solution. Sound judgment in determining the proper course of action in handling problems helps assure both the quality of the survey and the meeting of survey schedules.
Leveling instruments, as well as all surveying instruments and equipment, must be cared for and handled properly. Pay special attention to avoid any sudden shocks, jolts, and bumps which will require retesting of the instrument. A damaged or disturbed scientific instrument, however minor, can adversely affect correct and accurate results. Before using leveling equipment, inspect for signs of physical damage.
An engineer�s level is a precision instrument containing many delicate and fragile parts. All movable parts should work easily and smoothly when unlocked. When a part resists movement, do not use force; forcing a part to move will likely damage the instrument. Do not over-tighten clamps, as doing so can cause unwarranted wear and possible damage.
To ensure easy movement, lubricate the threads and bearing surfaces on movable parts, and always clean the parts before lubricating.
When oiling the parts, use only fine instrument oil. Do not use too much oil; excess oil gathers dust and also thickens, which interferes with the movement of the parts. This is especially true in cold weather where low temperatures cause oil to congeal. Use graphite powder as lubricant in cold weather conditions.
Store the level in its case when it is not in use and when transporting it to and from the job site. Tighten the level and clamp screws enough to prevent motion of the parts when it is inside the case. The case�s strong construction and padding are designed to reduce the effect of jarring and protect the level from damage. When transporting the level by vehicle, place the carrying case midway between the vehicle�s front and rear wheels. This is the point where bouncing of the wheels is minimized.
Never lift the instrument out of the carrying case by grasping the telescope. Wrenching the telescope in this manner can damage a number of delicate parts. Always lift the instrument out of the case by grasping the footplate or the level bar.
When you carry the instrument and the tripod from one setup point to another, loosen the level and clamp screws slightly. The screws should be tight enough to prevent the telescope from swinging and the instrument from sliding on the footplate, but loose enough to allow �give� in case of an accidental bump against an obstacle. You can carry the instrument over your shoulder like a rifle if the terrain to be traveled is free of obstacles, as shown in Figure 15-7.
Figure 15-7 � Carrying surveying instrument.
A surveyor�s umbrella should be used to avoid the effects of sunlight. If there is a great difference between the working temperature and the instrument storage temperature, the instrument should be acclimated to the actual working conditions approximately 15 minutes before observations begin.
The rodman is responsible for holding the leveling rod. The actions of a rodman in positioning and holding the rod affect the speed and accuracy of the leveling operation. The rodman is also responsible for taking care of the rod during and after the leveling operation. The rodman�s duties include the following:
Figure 15-8 � Correct stance for holding level.
A leveling rod is a precision instrument that has to be treated with care. Most rods are made of carefully selected, kiln-dried, well-seasoned hardwood with metal scale faces on which the scale graduations are painted. A rod should be handled with care; otherwise, the painted faces become scratched, dented, or damaged. Damage rods can make readings difficult and inaccurate.
Letting an extended rod close �on the run� by allowing the extended upper section to drop tends to damage both sections of the rod and the vernier. Always close an extended rod by easing down the upper section.
A rod will read accurately only if it is perfectly straight. Do not lay it down flat unless it is supported throughout on a flat surface. Do not use it as a support or as a lever. Store the rod in a dry place to avoid warping and swelling from dampness. Always wipe a wet rod dry before stowing it away.
Rinse mud off the rod, but do not scrub it. Use a mild soap solution to remove grease. Repeated washings with strong soap solutions will eventually cause the painted graduations to fade.
Consistently accurate and efficient leveling operations require teamwork between the instrumentman and the rodman. Survey accuracy is dependent upon many factors, including the refinement with which the line of sight can be made horizontal by the instrumentman, the ability of the rodman to hold the rod vertically, and the precision with which the rod reading is made. Some of the basic procedures and preparations applicable to direct leveling are presented below.
Terrain and atmospheric conditions are considerations that affect the selection of setup points. It is important to select a point where rod readings of the BS and FS points can be easily observed. To achieve balanced shots, a setup point should be approximately equidistant from both BS and FS. When in doubt, use shorter setup distances because they will result in smaller instrument error that can be caused by atmospheric refraction and the curvature of the earth.
The average instrument height at any setup is approximately 5 feet (1.5 meters). On even downhill slopes, the ground where the instrument is set up may not be more than 3 to 5 feet below the TP for a level BS. On the FS, the extended rod can be held on the ground about 8 feet (2.5 meters) below the instrument ground level and still permit a reading to be taken. This means that the tendency will be to make FS distances longer going downhill and to make BS distances longer going uphill.
It is good practice to conduct a reconnaissance of the terrain before starting leveling operations. Probable locations of instrument setup and TPs should be noted as a part of the reconnaissance. During the reconnaissance, look through a hand level to estimate the line of sight.
To set up a tripod, first hold two tripod legs with both hands and spread the tips of the legs a convenient distance apart. Then bring the third leg to a position that approximately levels the top of the protector cap when the tripod stands on all three legs. Then unscrew the protector cap.
Next, lift the instrument out of the carrying case by the footplate or level bar, and set it gently and squarely on the tripod head threads. Rotate the footplate counterclockwise one-fourth turn or until the instrument seats. Then rotate it clockwise to engage the head nut threads to the tripod head threads. If the threads do not engage smoothly, stop; they may be cross-threaded. Do not force the head if you encounter resistance; back it off, square up the instrument, and gently try to engage the threads. When they are engaged, screw the head nut up firmly but not too tightly. Setting up the instrument too tightly causes eventual wearing of the threads, making unthreading difficult.
After attaching the instrument and assuming the tripod is on stable soil, thrust the tripod leg tips into the ground far enough to ensure stable support, taking care to keep the footplate approximately level. Some tripods have legs equipped with short metal stirrups. The stirrups are used to force the legs� tips into the ground by foot pressure.
When setting a tripod on a hardened surface such as concrete, make sure the tripod�s legs do not accidentally spread, causing the tripod to collapse. Figure 15-9A shows the tripod�s leg tips inserted in cracks in a concrete pavement. In Figure 15-9B, the legs are held by an equilateral wooden triangle called a floor triangle.
Figure 15-9 � Two ways of preventing tripod legs from spreading on hard surfaces.
Just as a rodman must concentrate on keeping the rod perfectly plumb, the levelman must constantly remember that the line of sight through the telescope must be perfectly level in every direction or every reading made with the instrument will be inaccurate. After the level has been placed, the levelman performs the following procedures to level the instrument.
Align the telescope with a pair of level screws by turning them in opposite directions, as shown in Figure 15-10, until the bubble in the level vial is in the exact center.
Figure 15-10 � Manipulating level screws.
It is helpful to know that the bubble in the level vial moves in the direction that the instrumentman�s left thumb moves. To put this another way: Turning the lefthand screw clockwise moves the bubble to the left; turning the left-hand screw counterclockwise moves it to the right. When the bubble is centered with the telescope over one pair of screws, train the telescope over the other pair and repeat the process. As a check, swing the telescope over each pair of screws in all four possible positions to make sure the bubble is centered in each position.
The instrumentman makes a direct rod reading by viewing the graduation on the rod that is in line with the horizontal cross hair. With the exception an architect�s rod, leveling rods are graduated in feet and subdivided to the nearest 0.01 foot. This means direct readings are typically read to the nearest 0.01foot. Figure 15-11 shows a direct reading of 5.76 feet on a Philadelphia rod. Each black graduation and each white interval represents 0.01 foot.
Figure 15-11 � Direct reading of 5.76 feet on a Philadelphia rod.
The black numeral 7 in Figure 15-11 is the only numeral of the reading 5.76 feet that appears in the view. The red numeral 5 would not be visible through the telescope unless the sight distance was farther away. For this reason, the instrumentman would signal the rodman to �raise for red,� as described in the previous lesson.
To make sure the readings for tenths and hundredths are related to the correct whole-foot red numeral, it is best to make a direct reading as follows:
There are situations when target readings are used instead of direct readings. The three most common situations include these:
For target readings up to 7.000 feet, the Philadelphia rod is fully closed and read on the face by the rodman. The rodman sets the target on the face by the signals from the instrumentman, who determines when the horizontal axis of the target intercepts the horizontal cross hair.
When the instrumentman signals �all right,� the rodman clamps the target in place with the target screw clamp, as shown in Figure 15-12. The rodman then reads the target vernier, shown in the same figure.
Figure 15-12 � Target reading on a Philadelphia rod.
The reading to the nearest 0.01 foot is indicated by the zero on the vernier. In Figure 15-12, the vernier zero indicates a reading of a few thousandths of a foot more than 5.84 feet. To determine how many thousandths over 5.84 feet, examine the graduations on the vernier to determine the one most exactly in line with a graduation on the rod. In Figure 15-12, this is the 0.003-foot graduation; therefore, the reading to the nearest 0.001 foot is 5.843 feet.
For target readings of more than 7.000 feet, the Philadelphia rod is extended and the rodman makes the reading on the back of the rod. In Figure 15-13, the back of the upper section of the rod is shown, graduated from the top down, from 7.000 feet through 13.000 feet. A rod vernier on the back also can be seen fixed to the top of the lower section of the rod, also read from the top down.
Figure 15-13 � Reading on the back of a Philadelphia rod.
For a target reading of more than 7.000 feet, the rodman, on receiving the signal to �extend the rod,� fixes the target on the face of the upper section all the way to the top of the upper section. While doing this, the rodman makes sure the target vernier is set at exactly the same reading indicated by the rod vernier on the back of the rod; the rodman then releases the rod screw clamp and slides the upper section of the rod slowly upwards until the instrumentman gives the signal �all right.� When the horizontal axis of the target reaches the level where it is intersected by the horizontal cross hair, the instrumentman gives the signal.
The following example explains the basic procedure for determining elevations during a leveling operation.
In Figure 15-14, there is a BM at Point A with a known elevation of 365.01 feet and a Point B whose elevation needs to be determined. To determine Point B�s elevation, first set up and level the engineer�s level approximately half-way between Points A and B. Next, level the instrument. After the instrument is leveled the instrumentman has a perfectly level line of sight that can be rotated around the horizon.
Figure 14 � Direct leveling procedure.
After the instrument is leveled, the line of sight elevation must be determined. Line of sight elevation or height of instrument (HI) is calculated by adding the known elevation (KE) and the backsight (BS) height. In this example, the known elevation of the BM (Point A) is 365.01 feet and the BS height (the rod reading) is 11.56 feet. Therefore, the BM elevation 365.01 plus the BS rod reading of 11.56 equals an HI of 376.57 feet. This means whichever direction the telescope is pointing, all points on the horizon intercepted by the horizontal cross hair have an elevation of 376.57 feet.
To determine the ground elevation at Point B, the instrumentman takes a foresight (FS) on a rod held at Point B. In this example, the rod reading is 1.42 feet. Because the elevation of the line of sight (HI) is 376.57 feet, the ground elevation at Point B is the HI minus the rod reading, or 376.57 � 1.42, which equals 375.15 feet.
The balancing of the FS and BS distances is important in leveling. The effect of curvature and refraction may be eliminated by balancing BS and FS distances; however, instrumental error is a far more important reason for careful balancing.
�Balancing shots� means equalizing as much as possible BS and FS distances by selecting turning points that are approximately an equal distance from both the BS and FS points.
No matter how carefully a telescope is leveled, it is likely to be slightly out of the horizontal. The possibility of inaccurate reading increases as the length of the sight increases. When the BS distance differs from the FS distance, the BS and FS errors will differ. If the distances are the same, the errors will be the same. Therefore, balancing shots eliminates the effect of instrument error.
To achieve balanced shots, pace off an equal number of steps for the BS and FS. The BS and FS distances should be kept under 300 feet except when necessary to pass or cross an obstacle.
Suppose the elevation of a point at the summit of a long slope needs to be determined, and the nearest BM is at the foot of the slope some 30 feet or so below the summit. To determine an elevation in this situation, turning points (TPs) as displayed in Figure 15-5 must be used. A turning point is defined as a point on which both a minus sight (FS) and a plus sight (BS) are taken on a line of direct levels.
Figure 15-15 �Turning points.
Assume the elevation of the BM in Figure 15-15 is correct. The accuracy of the summit elevation is dependent on how accurately the elevation of each intermediate TP is determined. This accuracy depends upon a number of factors, the most important of which include the following:
When the use of a point in unstable ground is unavoidable, use a turning point pin or turning point plate. Drive a pin into the ground to mark the turning point. If a regular pin is not available, you may substitute a marlinspike or a railroad spike. If the soil is too soft, use a plate to support a driven pin.
| Test Your Knowledge 4. What type of lubricant is recommended for use on engineer�s levels in arctic regions?
5. When a level setup must be transferred to another point or station, what screws should be loosened slightly?
6. To help the instrumentman obtain accurate readings, the rodman should take which of the following actions?
7. The proper care of a leveling rod includes which of the following actions?
8. In determining the elevation of an unknown point, what arithmetic operation should you apply to the HI and FS?
9. When turning points are located in sandy soil, you must set the level rod on a base. Which of the following bases is an acceptable choice?
|
Leveling methods are subdivided into two major categories: direct and indirect. Direct leveling describes the method of measuring vertical distance (difference in elevation) directly with the use of precise or semi-precise leveling instruments. Indirect leveling is the measurement of vertical distances indirectly or by using computation. Unlike direct leveling operations, indirect leveling operations do not depend on lines of sight or visibility of points or stations. Two of the surveying instruments used for indirect leveling are the transit and the theodolite.
Direct leveling uses the measured vertical distance to carry elevation from a known point to an unknown point. Direct leveling is the most precise method of determining elevation, yielding accuracies of third or higher orders. When this method is specified for lower accuracy surveys, direct leveling is sometimes referred to as �spirit� or �fly� levels. Fly leveling operations are used to rerun original levels to ensure no mistakes have been made. Fly levels use a shorter route and smaller number of turning points than the original survey.
Differential leveling (also called direct leveling) is generally used in determining elevations of points to establish a chain or network of BMs for future use. It requires a series of instrument setups along the survey route. This type of leveling is frequently used for determining elevation during construction surveys. As shown in Figure 15-16, the basic procedure used to determine elevations in a differential leveling operation is the same as previously discussed.
Figure 15-16 � Differential leveling.
After the FS is completed, leave the rod on that point and move the instrument forward. Set up the instrument approximately midway between the old and new rod positions. The new sighting on the back rod becomes a BS, and now establishes a new HI. The points other than the BMs or TBMs on which the rods are held for the BSs and FSs are called turning points (TPs). Other FSs made to points not along the main route are known as sideshots. This procedure can be used as many times as necessary to transfer a point of known elevation to another distant point of unknown elevation.
Figure 15-17 shows a sample differential leveling run. The rod is held on BM 35 (Elev. = 133.163). The level is set up midway between BM 35 and TBM 16. The BS reading of +6.659 is added to the elevation of BM 35 and gives the resulting HI (139.822). The rod is moved to Peg 16 (which later becomes TBM 16). The FS reading of - 4.971 is subtracted from the HI to get the elevation of Peg 16. Note that the distance (220 feet each way) is also recorded for balancing. The process continues until BM 19 is reached. ,
Figure 15-17 � Sample notes and profile of a differential-level circuit.
When making level computations, check the notes for a level run to ensure the correct BM and elevation are used. Then, check the arithmetical accuracy where BSs are added and FSs are subtracted. The difference between the sum of the BSs taken on BMs or TPs and the sum of the FSs taken on BMs or TPs should equal the difference in elevation between the initial BM or TP and the final BM or TP.
Balanced BS and FS distances are shown in Figure 15-17. The distance used for the first instrument setup was 220 feet. The first BS (rod reading on 35) was 6.659 feet. The first FS (rod reading on 16) was 4.971. Notice that the plus sign (+) appears at the top of the BS column and that the minus sign (�) appears at the top of the FS column in the field notebook. This serves as reminder that BSs are added and FSs are subtracted as new elevations are computed.
The BS taken on a point added to the elevation of the point gives the HI. This establishes the elevation of the line of sight so that an FS can then be taken on any point (BM, TBM, or TP).
The elevation of 35 is 133.163 feet. The first HI is
133.163 + 6.659 = 139.822 feet.
The FS subtracted from the HI,
139.822 � 4.971 = 134.851 feet,
which is the elevation of 16.
Following through with a similar computation for each setup, notice the elevation of 19 is 136.457 feet.
Look now at the notes in Figure 15-17. The sum of all the BSs is 24.620 feet. The sum of all the FSs is
21.326 feet. The difference between the sum of the BSs and the sum of the FSs is
24.620 � 21.326 = 3.294 feet.
This difference should agree with the difference between the actual elevation of BM 35 and the elevation already found for BM 19, which is 136.457 � 133.163 = 3.294 feet.
This provides a check on the step-by-step computation of elevations.
Level lines that begin and end on points with fixed elevations, such as BMs, are often called level circuits. When leveling is accomplished between two previously established BMs or over a loop that closes back on the starting point, the elevation determined for the final BM seldom equals its previously established elevation. The difference between these two elevations for the same BM is known as the error of closure. The Remarks column of Figure 15-17 indicates the actual elevation of BM 19 is known to be 136.442 feet. The elevation found through differential leveling was 136.457 feet. The error of closure of the level circuit is
136.457 � 136.442 = 0.015 foot.
Based on the results recorded in Figure 15-17 it is assumed errors occurred progressively along the line over which the leveling was done so that adjustments for these errors are distributed proportionally along the line. Notice in Figure 15-17 the total distance between BM 35 and BM 19 is 2,140 feet and the elevation on the closing BM 19 is found to be 0.015 foot greater than its known elevation. Therefore, adjust the elevations found for the intermediate TBMs 16, 17, and 18.
The amount of correction is calculated as follows:
| Correction = | (Error of closure) x (distance between the starting BM and the intermediate BM) |
| distance between the starting and closing BM |
TBM 16 is 440 feet from the starting BM. The total length distance between the starting and closing BMs is 2,140 feet. The error of closure is 0.015 foot.
Correction = (0.015) x (440) = −0.003 ft 2140
The adjustments for intermediate TBMs 17 and 18 are made in a similar manner.
Reciprocal leveling is used for either differential or trigonometric leveling when a long sight across a wide river, ravine, or similar obstacle is required. Long sighting is affected by curvature and refraction and by any small error in aligning the line of sight with the bubble axis on the level. The alignment error is minimized by balancing the long sight and computing the curvature. The atmospheric conditions can vary so much over an open expanse that the refraction correction can also be quite erratic. Reciprocal leveling is used to minimize the effect of the atmosphere as well as the line of sight and curvature corrections. To reduce error using reciprocal leveling, use the following procedures:
Figure 15-18 � Reciprocal leveling.
The instrument is set up at point A and leveled carefully. A BS reading is taken on the N rod and a FS on the F rod. These readings are repeated several times. The instrument is moved to point B, set up, and carefully leveled with the rods remaining at their respective stations. A BS is taken on the N rod and an FS on the F rod, and repeated several times. Since instrument leveling is especially critical on reciprocal leveling, the instrumentman must center and check the bubble before each reading. If it is off-center a slight amount, the procedure must be repeated. The difference in elevation between N and F is computed from the readings at A and from the readings at B separately. Because of the errors in the long sight, the two results will have slightly different values. Note, however, that the long sight is an FS from A and a BS from B. The true difference in elevation is the average of both values, since the errors have opposite signs and will cancel each other.
In surveying, a profile is a vertical section of the earth measured along a predetermined or fixed line. In practice, profiles are a series of ground elevations determined by differential leveling or other methods that, when plotted along some line such as the center line of a road, can be used to determine the final grade or alignment of the road, railroad, or sewer line. Profiles are also used to compute volumes of earthwork such as determining the depth of fill or cut required to bring an existing surface up to or down to the grade elevation required for a highway.
Profile leveling provides data relative to the center line. In Figure 15-19, the top of the graph has information on the depth of cut or fill required at each station to bring the existing surface to grade. The prescribed grade line for the highway is indicated by the smoothly curved grade line shown. The cut or fill at each station is determined by counting the squares between the profile and the grade line.
Figure 15-19 � Plotted profile and grade lines along proposed road center line.
Figure 15-19 shows a plotted profile of the existing ground surface along a proposed highway center line. Horizontally on the graph is a succession of 100-foot stations, from 0 + 00 to19 + 00.
The elevations run vertically. Each horizontal interval between the adjacent vertical grid lines represents 25 feet. Each vertical interval between adjacent horizontal grid lines represents 2.5 feet.
The profile is plotted through a succession of points, each of which was identified from a profile elevation taken on the ground. Figure 15-20 shows field notes for the levels taken from 0 + 00 through 10 + 00.
Figure 15-20 � Field notes for profile levels shown in Figure 15-19.
The level was first set up at a point approximately equidistant from station 0 + 00 and from a BM identified as National Geodetic Survey Monument, Bradley, Missouri. The elevation of the BM was 117.51 feet. The first backsight reading on a rod held on the BM was 7.42 feet. Therefore, the HI which is entered into the HI column of the field notes is
117.51 + 7.42 = 124.93 feet.
From the first instrument setup, FSs were taken on station 0 + 00 and 1 + 00. The elevation of the station in each case was determined by subtracting the FS reading from the HI. Note that the FS taken on station 1 + 00 is entered in a column headed FS, while the one taken on station 0 + 00 is entered in a different column, headed IFS. IFS is an intermediate FS, or an FS taken on a point that is neither a BM nor a TP. Station 1 + 00 is used as a TP in shifting the instrument ahead. Only FSs taken on BMs or TPs are entered in the column headed FS.
After an FS was taken on station 1 + 00, it became necessary to shift the instrument ahead. Station 1 + 00 was used as the TP. From the new instrument setup, a BS was taken on a rod held on 1 + 00. The new HI was found by adding the BS reading to the previously determined elevation of 1 + 00.
From the new setup, an FS was taken on station 2 + 00; again, the elevation was found by subtracting the FS reading from the HI. After this sight was taken, the instrument was again shifted ahead, probably because of the steepness of the slope. This time, station 2 + 00 was used as the TP2. From the new setup, a BS was taken on station 2 + 00 and 15-24 a new HI established. From this setup, it was possible to take FSs on both station 3 + 00 and station 4 + 00. Because station 3 + 00 was not used as a TP, the FS on it was entered under IFS.
Apparently, the slope between station 4 + 00 and station 5 + 00 was so steep that sighting both stations from the same setup with the rod being used was impossible. Consequently, an intermediate TP (TP4) was established at station 4 + 75 by determining the elevation of this station. The instrument was shifted to a setup from which a BS could be obtained on a rod held on this station and from which FSs on stations 5 + 00, 6 + 00, 7 + 00, and 8 + 00 could be taken. Station 8 + 00 was then used as a TP for the last shift ahead. From this last setup, it was possible to take FSs on stations 9 + 00 and 10 + 00.
As a check on the arithmetic, recheck each page of level notes to check the difference between the sum of the FSs and the sum of the BSs against the difference in elevation between the initial BM or TP and final BM or TP. Obviously, only the BSs and FSs taken on BMs and TPs are relevant to this check. This is why intermediate FSs not taken on BMs or TPs are entered in a separate column.
If the arithmetic is correct, the two differences will be the same. As can be seen, the sum of the relevant BSs in Figure 15-20 is 39.63, the sum of the FSs is 27.70, and the difference between the two is 11.93. Note that from this difference, the BS taken on TP5 is deducted. The reason is the fact that this BS is not offset by a corresponding FS on a BM or TP. With the BS taken on TP5 deducted, the difference between the sum of the FSs and the sum of the BSs is 6.86. The difference between the elevation of TP5 and the elevation of the initial BM is 6.86, so the arithmetic checks.
Remember, this procedure provides a check on the arithmetic only. If incorrect values are recorded, the arithmetic will check out as if the correct values had been recorded.
Just as Profile leveling is used to determine the elevations of a series of points lengthwise along a highway, Cross-section leveling is used to determine the elevations of points on a succession of lines running at right angles or perpendicular to a lengthwise line of the highway.
Cross-section lines are established at regular stations, at any plus stations, and at intermediate breaks in the ground. Short cross lines are laid out by eye. Long cross lines are laid out at a 90� angle to the center line with the transit. For short cross lines, most surveyors prefer to use an angle prism for sighting 90� angles from the center line.
For cross-section leveling and strip topography, it is necessary to lay off a 90� angle at numerous points along a center line. Surveyors can often establish the 90� angle with sufficient accuracy by estimation. Straddle a point on the line and then, extending your arms sideways along the marked line, as shown in Figure 15-21, look alternately right and left, and adjust your foot position until your body is in line with AB. Then bring your hands together in front of you, pointing along an approximate 90� line from the marked line. Experienced surveyors can lay off a 90� angle using this method so that a point 100 feet away is within 1 foot of the true perpendicular.
Figure 15-21 �Laying off a 900 angle from the center line stakes.
Measure elevations consisting of abrupt changes or breaks in the ground with a rod and level. Use a metallic tape to measure all distances from the center line. In rough country, you can use the hand level to obtain cross sections if the center-line elevations have been determined by an engineer�s level.
Cross-section leveling is usually done with a hand level after the profile run has been made, the profile run has been established, and the center-line elevation at each station is known. The method is as follows.
Suppose cross-section elevations at 10-foot intervals for 40 feet on either side of the center line are needed. To find these elevations, first determine the vertical distance from the ground to the line of sight through the hand level while standing erect with the level to your eye. The best way to do this is to sight on a level rod held plumb in front. Suppose the vertical distance is 5.5 feet. Then the HI at any center-line station is the center line elevation (obtained in the profile level run) plus 5.5 feet.
At station 0 + 00, as shown in Figure 15-22, the elevation is 122.53 feet. The HI is 122.53 + 5.5 = 128.03 feet. With the elevation rounded off to the nearest 0.1 foot, the elevation is 128.0
Figure 15-22 �Sample field notes from cross-section leveling at first three stations shown in figure 15-20.
As rodman, if you hold a rod 40 feet to the left of the center line at station 0 + 00 and read 1.9 feet on the rod, then the elevation of the point plumbed by the rod is 128.0 � 1.9 = 126.1 feet.
Now if you move on to a point 30 feet from the center line at station 0 + 00 and read 3.3 feet on the rod, the elevation of the point is 128.0 � 3.3 = 124.7 feet.
This process is used to determine the elevations at all the required points on the cross section. This same process is repeated for each cross section.
Cross section notes are recorded in the field book using two basic methods. The first, and often preferred, method begins at the bottom of the page and is read upward, as shown in Figure 15-22. This method helps to keep orientation in the direction the line runs and helps to prevent confusion as to which is the right or left side of the line. It reduces the possibility of recording readings on the wrong side of the center line.
With the second method, notes are recorded in the conventional manner of reading from top to bottom of the page. Whichever method is used, the recorder must stand facing the direction in which the line runs; left and right in the notebook must correspond to left and right in the field.
Figure 15-22 shows field notes for cross-section levels taken on the first three stations shown in Figures 15-19 and 15-20. On the data side, only the station and the HI need to be listed. On the remarks side, each entry consists of a point elevation, written over the distance of the point from the center line. The computed elevation, determined by subtracting the rod reading from the HI, is written in above. Note the rod reading at the center line is the 5.5-foot vertical distance from the line of sight to the ground. Also, notice the center-line elevation written in at each station is obtained in the profile level run. The HI for each station is calculated by adding the two figures together.
Double rodding is a form of differential leveling in which a continuous check is maintained on the accuracy of the leveling procedure. Double rodding is typically done by two rodmen; however, it is possible to carry out the procedure using only one rodman.
In double rodding, the HI is determined at each setup point by backsights taken on two different TPs. If no mistake or large error has been made, the result will be two HIs that differ slightly from each other. Elevations computed this way will also differ slightly. In each case, the average is taken as the elevation.
Figure 15-23 shows double-rodded level notes for a run from one BM to another by way of three intermediate TPs. In each case, a �higher� TP (TP1) and a �lower� (TP1L) were used, resulting in two different HIs for each. Computed by way of the higher HIs, the elevation of BM2 came to 851.98 feet. Computed by way of the lower HIs, it came to 852.00 feet. The mean (average) of 851.99 feet was taken as the correct elevation.
Figure 15-23 � Sample field notes from double-rodded levels.
Indirect methods of leveling include both trigonometric and barometric leveling. Trigonometric leveling uses vertical angles and a horizontal distance to compute the difference in elevation. Barometric leveling uses the difference in atmospheric pressures that are observed by a barometer or an altimeter to determine the elevation differences. Indirect methods of leveling are discussed at the advanced engineering tech level.
| Test Your Knowledge 10. The original level run is rapidly rerun as a check in what type of leveling procedure?
11. Simultaneous-reciprocal leveling requires which of the following level party personnel?
12. At what point(s) along a proposed highway are cross sections taken?
13. What is a form of differential leveling in which a continuous check is maintained on the accuracy of the leveling procedure?
|
Like all other surveying operations, leveling is carried out by following a prescribed order of precision. This means the instruments must be properly handled and the methods used to survey must be followed in order to achieve specific standards of accuracy.
First-order leveling is used to establish the main level network for an area and provides basic vertical control for the extension of level networks of the same, or lower, accuracy in support of mapping projects, cadastral (recording property boundaries, subdivision lines, buildings, etc.), and local surveys. Level lines must start and end on proven, existing BMs of the same order. New levels must be run between the starting BM being used and at least one other existing BM and must show there is no change in their relative elevations.
Second-order leveling is used to subdivide nets of first-order leveling and provides basic control for the extension of levels of the same, or lower, accuracy in support of mapping projects and local surveys. Second-order levels are divided into two classes: Class I and Class II. Class I is used in remote areas where the line must be longer than 25 miles because routes are unavailable for the development of additional or higher order networks and for spur lines. Class II levels are used for the development of nets in more accessible areas. Class I leveling, requires that all lines start and close on previously established BMs of first or second order. New levels have to be run between the existing BM being used and at least one other existing BM to prove they have not changed their relative elevations. The criteria for Class II are the same as for Class I, except Class II lines are run in one direction only.
Third-order leveling is used to subdivide an area surrounded by first- and second-order leveling and to provide elevations for the immediate control of cadastral, topographic, and construction surveys for permanent structures. The following criteria should be observed in third order leveling:
Fourth-order leveling is used to subdivide an area within a third-order network. This method is used in connection with the location and construction of highways, railroads, and other engineering works. In practice, trying to shoot for a higher degree of accuracy is advantageous if it does not affect work progress. The following criteria should be observed in fourth-order leveling:
The instruments commonly used in third- and fourth-order leveling are the engineer�s level and the Philadelphia rod. The adjustments of these instruments should always be checked before use.
The precision of a level run is usually prescribed in terms of a maximum error of closure. Maximum error of closure is obtained by multiplying a constant factor by the square root of the length of the run in miles or in kilometers, depending upon the system 15-30 of measurement being used. The Federal Bureau of Surveying and Mapping specifies certain requirements and the maximum closing errors, such as those shown in Figure 15-24. Refer to this standard if the order of precision is not specified for a particular survey project.
Figure 15-24 � Federal Bureau of Surveying and Mapping requirements.
A level run that begins at a particular BM and is carried back to the same BM is called a level loop. A run that does not close on the initial BM is called a level line. A level line closes on another BM. However, when a level line is carried back to its origin, it becomes a level loop. A level line is usually carried back to the initial BM to determine the error of closure.
Error of closure is simply the difference between the known elevation of the initial BM and the elevation of the same BM as computed in a level run.
The allowable error of closure depends on the precision required (first, second, or third order). The permissible (or allowable) error of closure in accuracy leveling is expressed in terms of a coefficient and the square root of the horizontal length of the actual route over which the leveling was done.
Most differential leveling (plane surveying) is third-order work. In third-order leveling, the closure is usually made on surveys of higher accuracy without doubling back to the old BM at the original starting point of the level circuit. The length of the level circuit, therefore, is the actual distance leveled. For third-order leveling, the allowable error is
0.050 ft � length of the the level circuit in miles
After adding the sight distances in the sixth and seventh columns of the differential level circuit shown in Figure 14, the length of the level circuit is 2,140 feet. The length in miles is 2140 / 5280 = 0.405. The allowable error of closure is
0.050 ft 0.405 = 0.050(0.64) = 0.032 ft Since the actual error is only 0.015 foot, the results are sufficiently accurate. First- and second-order levels usually close on themselves. The leveling party runs a line of levels from an old BM or station to the new BM or station, and then doubles back to the old BM for closure. The actual distance leveled is twice the length of the level circuit. For second-order leveling, the allowable error is 0.035 ft theoflength circuitlevel in miles First-order leveling is still more precise. The allowable error cannot be greater than 0.017 ft theoflength circuit level in miles
The terms �mistakes� and �errors� are not synonymous in surveying. Leveling operations, like other survey measurements, are susceptible to both. Mistakes can be avoided by a well-arranged system of operation and an attention to detail by all of the survey party members. Checking and rechecking, as described in some of the operations, eliminate many mistakes. While errors cannot be completely eliminated, errors can be minimized so their effect on survey accuracy is small and within allowable tolerances.
The leveling mistakes discussed here are not intended to include all possibilities but rather to list examples of commonly occurring mistakes. The survey party personnel should be aware of these possibilities and should be careful to avoid them. Some of the common mistakes are as follows:
Generally, errors cannot be completely eliminated; however, they can be contained within acceptable tolerances. Minimizing errors requires using prescribed methods and instruments. Reducing errors may also include applying mathematical corrections. Some of the conditions that produce errors are listed below.
| Test Your Knowledge 14. Recording a rod reading in the wrong column in a field book is classified as a ______
15. Between errors and mistakes, the most importance difference, if any, is that ______
|
An engineering survey forms the first of a chain of activities which ultimately leads to a completed structure of some kind, such as a building, a bridge, or a highway. An engineering survey is usually subdivided into a design-data survey and a construction survey.
This section discusses the basic engineering surveys commonly performed by an engineering tech survey party in support of military construction activities. Various types of occupational hazards relating to specific surveying operations are also presented here, together with the precautions or applicable abatement procedures that must be carried out to deter injury to the survey crew and/or damage to surveying equipment or material.
Surveys for roads and streets involve both field work and office work. The extent of each type of work depends on the magnitude and complexity of the job. Some phases of the work may be done in the field or in the office. The decision as to which procedures are to be followed is influenced by the number of personnel available and by the experience and capabilities of the individuals involved.
The design-data survey is conducted to collect information essential for planning an engineering project or development and estimating its cost. A typical design-data survey, for example, is a route survey required in the design and construction of a particular road or highway. The initial activities included in a route survey are a reconnaissance survey, a preliminary location survey, and a final location survey.
A reconnaissance survey provides data that enables design engineers to study the advantages and disadvantages of a variety of routes in order to determine the most feasible one. Reconnaissance begins by finding all existing maps showing the area to be reconnoitered. In reconnaissance, studying existing maps is as important as the actual fieldwork. Studying maps and aerial photographs, if any exist, often eliminates an unfavorable route from further consideration, thus saving the reconnaissance field party considerable time and effort.
Contour maps provide essential information about area relief. Aerial photographs provide a quick means for preparing valuable sketches and overlays for the field party. Direct aerial observation provides an overview of an area that speeds up later ground reconnaissance if the region has already been mapped.
Begin the study of a map by marking the limits of the area to be reconnoitered and the specified terminals to be connected by the highway. Note whether or not there are any existing routes. Note ridgelines, water courses, mountain gaps, and similar control features. Look for terrain that permits moderate grades without too much excavating. Use simplicity in alignment and have a good balance of cuts and fills. Use a profile arrangement that makes it possible to fill depressions with the cut taken from nearby high places.
From the map study, determine grades, estimate the amount of clearing required, and locate routes that keep excavation to a minimum by taking advantage of terrain conditions. Mark stream crossings and marshy areas as possible locations for fords, bridges, or culverts.
The reconnaissance field party should follow the route or routes marked earlier during the map study. Field reconnaissance is an opportunity for checking the actual conditions on the ground and for noting any discrepancies in the maps or aerial photographs. Make notes of soil conditions, availability of construction materials such as sand or gravel, unusual grade or alignment problems, and requirements for clearing and grubbing. Take photographs or make sketches of reference points, control points, structure sites, terrain obstacles, landslides, washouts, or other unusual circumstances.
The reconnaissance survey party usually carries lightweight non-precision instruments. A compass is used to determine direction and angles. An aneroid barometer or altimeter is used to determine approximate elevations. An Abney hand level (clinometer) is used to estimate elevations and to project level lines. Other useful items to carry include pocket tapes, binoculars, pedometer and pace tallies, cameras, watches, maps, and field notebooks.
Keep design considerations in mind while running a reconnaissance survey. Remember that future operations may require further expansion of the route system. Locate portions of the new route, whenever possible, along preexisting roads or trails. Locate routes on stable, easily drained, high-strength-bearing soils. Avoid swamps, marshes, low-bearing-strength soils, sharp curves, and routes requiring large amounts of earthmoving.
Keep the need for bridges and drainage structures to a minimum. When the tactical situation permits, locate roads in forward combat zones in concealed areas and protected from enemy fire.
After the field work is complete, a reconnaissance survey report is generated. The completed report provides data used to select the most feasible route or routes.
A preliminary survey is a more detailed study of one or more routes tentatively selected on the basis of a reconnaissance survey report. It consists of surveying and mapping a strip of land along the center line of a tentatively selected route. Some of the activities associated with preliminary survey include running a traverse (sometimes called a Pline or survey baseline), establishing BMs, running profiles, and taking cross sections. For many projects, the preliminary survey is conducted by a transit-tape party alone. Other projects may require a level party and a topographic party.
Normally, the data gathered from a preliminary survey is plotted while the party is in the field. This practice gives a more accurate representation of the terrain, reduces the possibility of error, and assists in resolving any doubtful situations while actually observing the terrain.
The final location survey, also called the location, is a continuous operation that goes on from the start of the project through to the end of the actual construction. The final location survey consists of establishing the approved layout in the field, such as providing the alignment, grades, and locations to guide the construction crew.
The engineering techs tasked with the final location survey normally start (in both time and distance) ahead of the construction crew in order to save construction time and to avoid delay of scheduled activities. Their activities include setting stakes to mark the limits of final earthmoving operations, locating structures, and establishing final grades and alignment.
The final location in the field is carefully established by the transit party, using the paper location prepared from the preliminary survey. The center line may vary from the paper location because of objects or conditions that were not previously considered. If variations are detected and changes are required, the changes must be approved by the engineering officer.
fter the type and general location of a highway are decided and the necessary design data is obtained in the field, a number of office tasks must be performed. The tasks include the following:
Repeat these operations one or more times as trial designs are developed and revised. Plot a highway plan and profile view on the same sheet. Figure 15-25 shows a plotted highway plan and profile view.
Figure 15-25 � Profile of highway.
Plotting the plan view of a highway is similar to a traverse except for the introduction of topographic details, curves, and curve data.
Profile plotting is done on regular profile paper that has ruled horizontal and vertical parallel lines, as shown in Figure15-25. The vertical lines are spaced 1/4 or 1/2 inch apart and the horizontal lines are spaced 1/20 or 1/10 inch apart.
The first consideration when conducting profile plotting is the selection of suitable horizontal and vertical scales for the profile paper. The selection of the scale varies with the character of the ground and other factors. In Figure 15-25, the horizontal scale used was 1 inch = 400 feet, and the vertical scale used was 1 inch = 20 feet. Normally, choose scales that are proportional numbers in multiples of ten.
To plot a profile, use profile level notes or use the elevations obtained from the contour lines. For the example in Figure 15-25, assume the profile level notes indicate the center line elevations at the indicated stations from 5 + 00 through 15 + 00.
Also for this example, the notes would show an elevation was taken at every full station and also at every station where a significant change in elevation occurs. This is true for station 8 + 75 where a significant elevation change occurs. If an elevation had not been taken at 8 + 75, the drop that exists between 8 + 00 and 9 + 00 would be indicated on the profile.
Notice at listed elevations that each was plotted as a point located where a vertical line that indicates the station intersected a horizontal line indicating the elevation of that station. Also note that usually stations are labeled where the line crosses highways, streams, and railroads.
Besides the profile of the existing terrain, the vertical tangents of the proposed highway center line are also plotted in Figure15-25. The end elevation for each of these (the elevations of points of vertical intersection (PVI) was determined by the design engineers. Various circumstances were considered when developing the proposed highway center line. One of the important considerations was the filling of each depression with an approximately equal volume of cut taken from a nearby hump or from two nearby humps.
The gradient, in terms of percentage of slope (total rise or fall in feet per 100 horizontal feet), is marked on each of the vertical tangents, as shown in Figure15-25. The percentage of slope is computed for a tangent as follows.
For the tangent running from station 6 + 00 to station 18 + 00, the total rise is the difference in elevation, or
417.0 � 413.3, or + 3.7 feet.
The horizontal
distance between the stations is 1,200 feet. The percentage of slope, then, is
the value of x in the equation
1200.00 = 100 = 0.31 or 31% 3.7 x
For a tangent running from station 18 + 00 to station 26 + 00, the total slope downward is the difference in elevation, or
412.0 � 417.0, or � 5.0 feet.
The distance between the stations is 800
feet. The percentage of slope then is the
value of x in the equation
800 = 100 = −0.6 = −62% −5.0 x
Figure 15-26 shows information found in a typical design cross section including the materials to be used along with their thicknesses.
Figure 15-26 � Typical design cross section.
For the purpose of staking out and for earthmoving calculations, the cross-section line of the existing ground at each successive station must be plotted. After each station is plotted, the design-data cross section (typical section of the highway) is then superimposed.
Figure 15-27 shows a designed cross section of a 40-foot-wide road taken from a station or point along the road center line. The elevation of the existing surface is 237.4 feet all the way across, which makes it a level section. The finished grade for the highway at the station is 220.4 feet. The prescribed side-slope ratio is 1.5:1, or a 1.5 horizontal unit for every one unit of vertical rise.
Figure 15-27 � Level section in cut.
Because the ground line across the cross section is level and the side-slope ratio is the same on both sides, the horizontal distance from the center line to the point where the side slope meets the natural surface is the same on both sides. Slope stakes are used to guide the earthmovers. The horizontal distance from the center line to a slope stake can be computed by methods that will be explained later.
In the case of this designed cross section, the data available includes the following:
Because the elevation of the level section in Figure 15-27 is the same on both sides, only a single-level shot elevation is needed. This type of section is called a one-level section, or a level section. Because the entire sectional area consists of material to be excavated or cut, it is called a section in cut.
In the section shown in Figure 15-28, the ground line across the section is sloping. To plot this section, three different elevations are needed: one for the left slope stake, one for the center-line grade stake, and one for the right slope stake. If these three levels are taken, the section is called a three-level section in cut. If additional levels are taken midway between the center line and the slope stake on either side, it is called a five level section in cut. It is a section in cut because the entire cross-sectional area consists of cut. Level, three-level, and five-level sections are called regular sections.
Figure 15-28 � Three-level section in cut.
Figure 15-29 shows a level section in fill. Figure 15-30 illustrates a three-level section in fill.
Figure 15-29 � Level section in fill. Figure
15-30 � Three-level section in fill.
The section shown in Figure 15-31 consisting of a cut and a fill is called a side hill section.
Figure 15-31 � Side hill section.
Cross sections may be preliminary or final. Preliminary cross sections are irregular sections plotted before the finished grade is determined. Preliminary cross sections may be identified by levels run in the field or by elevations found on the contour lines of a topographic map.
Final cross sections are sections of the final road design. They may be prepared in the same manner as preliminary sections, or they may be regular sections plotted from field data obtained after the finished grade is set. The term �final cross section� is also applied to as-built sections taken after construction is completed.
Cross sections are usually plotted on cross-section paper. Commonly called 10 x10- inch paper, it is ruled into 1-inch squares with heavy orange or green lines, and with lighter lines into 1/10-inch squares.
Each cross section is plotted separately. The station number appears below each cross section. The first cross section is placed at the top of a sheet and continued downward until all sections are plotted. Two or more sections may be plotted on the same sheet. For a major highway project, the cross sections can be plotted on a continuous roll of cross-section paper. Some surveyors prefer to plot the cross sections from the bottom to the top of the paper. They may also prefer to record cross-section notes in the same manner. If you follow these methods of plotting and recording, you are properly oriented with the actual direction of the highway. This means your left is also towards the left of the highway. It is also to the left of the cross section notes and the plotted cross section. It does not matter which method is used as long as proper orientation is maintained.
Unlike profile plotting, in cross-section plotting, the same scale is often used for both the vertical and the horizontal distance. Common scales are 1 inch = 5 feet and 1 inch = 10 feet. When sections are shallow, it is best to exaggerate the vertical scale, making it from two to ten times the horizontal scale.
For the center line for a row of sections, use one of the heavier vertical lines on the paper far enough away from the margin so plotted points will not run off the paper. Note the depths indicated for the first section to be plotted, and select a horizontal line for the base approximately centered between the top and bottom margins. Mark this with the base elevation. Then lay off the horizontal distances of the section surface elevations on either side of the center line, and plot the elevations by using the level data. Finally, connect the plotted points by using a straightedge or by drawing freehand lines.
In Figure 15-32, cross-section notes are shown for the existing ground along a proposed road. In Figure 15-33, the sections at stations 11 + 00 and 11 + 43 have been plotted. For each station the field party took the ground elevation 40 feet to the right and to the left of the center line. For each station, however, the center-line distance of the intermediate elevations varies making these irregular sections
Figure 15-32 � Cross section notes.
The HI for both plotted stations is 76.70 feet. For the point 6 feet left of the center line at station 11 + 00, note the 4.2 written below the 6. This reading was obtained from a rod held on this point. The number 72.5 shown in the parentheses right below the number 4.2 is the elevation of this point. You obtain the elevation by subtracting from the HI, the rod reading FS: 76.70 � 4.20, or 72.50
This point is plotted 6 feet to the left of the center line at an elevation of 72.5 feet, as shown in Figure 15-33. Notes are reduced in the office. The general practice is to print the elevations in RED. The elevation just computed (72.5) appears in red in the cross-section notes, as shown in Figure 15-32.
Figure 15-33 � Cross section plotted.
After the road gradients, either preliminary or final, are designed, plot the design-data cross section on the existing ground line section plot at each station to complete the picture of the end-area as it will be in the finished highway. Obtain the finished grade elevation for each station from the profile. Plot the finished grade point, usually located on the center at each cross section. Then draw in the outline of the pavement surface, ditches, and cut or fill slopes as they show on the typical design section. Plotting may be done with triangles. However, a faster method uses templates made of plastic, thin wood, sturdy cardboard, or other suitable material. Prepare templates for a cut section, a fill section, and a side hill section that may be flipped over to accommodate the direction of hillside slope.
The procedures just described are the most common and pertain to irregular sections. If regular sections are taken in the field after the gradients have been designed, then both the existing and the finished surfaces are plotted. Field notes for simplified three-level sections on a highway are shown in Figure 15-34.
Figure 15-34 � Field notes for three-level cross section.
On the data side, the profile elevation and the grade elevation at each station are listed. In the columns headed Left and Right on the remarks side, the upper numbers and letter symbols (C for cut, F for fill) indicate the amount of material to be removed or added. The numbers under the lines indicate the distance measured out from the center line. These points also indicate slope stake locations. If a five-level or irregular section is being recorded, additional points must be written between those for the center and for the slope stakes to indicate the changing elevations.
The design-data survey is followed by the construction survey, which consists of the layout or stakeout survey and the as-built survey. In a layout survey, both horizontal and vertical control points are located and marked to guide the construction crews. Figure 15-35 illustrates a typical arrangement of stakes and hubs used in highway or road construction.
Figure 15-35 � Typical arrangement of hubs and stakes on a road section (final grading).
The functions of the stakes and hubs include the following:
The first major step in highway construction is usually the rough grading or earthmoving which brings the surface up to or down to the approximate elevation prescribed for the sub-grade. The sub-grade is the surface of natural soil, or the place where the pavement will be laid. The sub-grade elevation, therefore, equals the grade (finished surface) elevation minus the thickness of the pavement.
In rough grading, the equipment operators are usually guided by grade stakes set along the center line by the transit-tape survey party at center-line stations. The center-line stations (stakes) are usually set at intervals of 100 feet or more on straight-line stretches and intervals of 50 feet or less on roads with horizontal and vertical curvatures. On a small-radius, street-corner curve, a center-line hub stake might be set at the center of the circle of which the curve is a part. This is done so the construction crew may outline the curve by swinging the radius with a tape. Reference stakes or hubs are also set on one or both sides of the center line to reestablish the center line at any time.
Each center-line stake is marked with the vertical depth of cut or fill required to bring the surface to grade elevation. The surveyor must indicate the station markings and the cut and fill directions on stakes. The starting point is the first station in the survey is numbered 0 + 00. The next station is normally 100 feet farther and is marked 1 + 00; the third station is another 100 feet farther and is marked 2 + 00, and so on. On sharp curves or on rough ground, the stakes may be closer together, as shown in Figure 15- 36. Generally, the station markings face the starting point. The mark on the side facing the starting point is used to indicate the stake is a center-line stake.
Figure 15-36 � Center-line layout.
The A cut is designated by the letter C, and the fill is indicated by the letter F. Numerals follow the letters to indicate the amount that the ground should be cut or filled. The symbol C15 indicates the existing ground should be cut 1.5 feet, as measured from the reference mark. During rough grading, the cut and fill are generally carried just up to the nearest half foot. Exact grade elevations are later marked with hubs (blue tops).The mark V is called a crowfoot. The apex of the V indicates the direction of the required change in elevation; so a cut is indicated by V, and a fill is indicated by upside down V. In some cases, surveyors mark the grade stake only with a negative or a positive number and the crowfoot, indicating the cut or fill.
Figure 15-37 shows a cut stake which is also a center-line marker. Note the station mark is written on the front of the stake and the construction information on the back. On grade stakes other than the center-line stakes, the construction information should be written on the front and the station marked on the back.
Figure 15-37 � Cut stake.
The stake shown in Figure 15-38 indicates fill is required. The letter F at the top of the stake stands for fill. The numerals indicate 2 feet of fill are required to bring the construction up to grade.
Figure 15-38 � Fill stake (not on center line).
Some stakes indicate that no cutting or filling is required. Figure 15-39 illustrates a grade stake on a proper grade on a center line. The word GRADE (or GRD) is on the back of the stake, and the crowfoot mark may not be indicated. Some surveyors prefer to use a crowfoot mark on all grade stakes. If this grade stake was not a center-line stake, the GRD mark would be written on the front of the stake.
Figure 15-39 � Stake on proper grade.
Points with the same ground and grade elevation are set by grade stakes. They are usually set after the center line is laid out and marked with hubs and guard stakes. They can be re-established if the markers are disturbed. Elevations are usually determined by an engineer�s level and level rod. One procedure used for setting grade stakes is as follows:
The elevations and the cuts or fills may be recorded in the level notes, or they may be set down on a construction sheet, as explained later in this lesson.
Another procedure may be used that combines the method listed above so that the computations may be completed while at each station. The cut or fill can be marked on the stake immediately.
As before, levels are run from BMs. The procedure at each station is as follows:
Figure 15-40 � Determining cut or fill from grade rod and ground rod.
Blue top hubs are used during the final grading. These hubs are driven into the ground until the top is at the exact elevation of the finished grade as determined by the surveying crew. When the top of the stake is at the desired finish grade elevation, it is colored with blue lumber crayon (keel) to identify it as a finished grade stake. Other colors may be used, but be consistent and use the same color keel throughout the project so as not to confuse the equipment operators. Blue tops are normally provided with a guard stake to avoid displacement during construction work. The guard stake usually shows the station and the elevation of the top of the hub. Setting blue tops is primarily conducted during final grading operations. The procedure is as follows:
Where grade stakes cannot be driven, for example in hard coral or rock areas, use ingenuity to set and preserve grade markings. Markings may often be made on the rock with a chisel or a keel.
Slope stakes are driven at the intersection of the ground and each side slope or offset a short distance. They indicate the earthwork limits on each side of the center line. The minimum areas to be cleared and grubbed extend outward about 6 feet from the slope stakes. Refer back to Figure 15-31 and take a close look at the position of the slope stakes. The horizontal distance of a slope stake from the center line varies. Three variables must be known to determine this distance:
1. The width of the roadbed, including widths of shoulders and ditches, if any
2. The side-slope ratio (expressed in units of horizontal run in feet per foot of vertical rise or fall)
3. The difference in elevation between the grade for the road and the point on the natural ground line where the slope stake will be set In Figure 15-41, d is the horizontal distance from the center line to the slope stake, W/2 is the horizontal distance from the center line to the top of the slope, h is the difference in elevation between the finished grade and the ground at the slope stake, and s is the slope ratio. The product of h x s gives the run of the slope or the horizontal distance the slope covers. The horizontal distance (d) of the slope stake from the center line, then, equals the sum of W/2 plus hs. For example, suppose W/2 is 20 feet, h is 10 feet, and the bank is a 4:1 slope. Figure 15-41 � Fill section level. 15-52 Then hs = 10 x 4, or 40 and d = 20 feet + 40 feet, or 60 feet In practice other factors must be considered, such as a transverse slope or the crossfall of the pavement (sometimes called the crown), ditches, and other factors. In Figure 15- 42, for example, there is a crossfall (h=) across W/2 so that the run (horizontal distance covered) of the bank (hbs) is the product of s x hb instead of hs, as in Figure 15-37, view A. The crossfall is usually constant and may be obtained from the typical design sect ion shown on the plans. Figure 15-43 shows a cut section in which W/2 varies with crossfall, side slope, ditch depth, and back slope. For example, assume that the distance from the center line to the beginning of the side slope is 20 feet, the cross fall totals 1 foot, the ditch depth is 1.5 feet, and both the side slope and back slope ratios are 2:1. The distance W/2, then, comprises horizontal segments as follows: 1. From the center line to the top of the slope, which is 20 feet 2. Then to the ditch flow line, which equals the product of slope ratio 2 times ditch depth (1.5), or 3 feet. 3. Then to the point on the back slope that is level with the finished center line, which equals slope ratio 2 times the difference in elevation crossfall plus ditch depth, 2(1 + 1.5), or 5 feet. 4. The total distance of W/2, is the sum of 20 + 3 + 5 or 28 feet. Figure 15-42 � Fill section with cross fall. 15-53
Slope stakes are usually set with an engineer�s or automatic level, a level rod, and a metallic or nonmetallic tape. In rough terrain, a hand level is generally used instead of an engineer�s level. If the engineer�s level is used, three crew members are generally employed for fieldwork. The three crew members include the instrumentman, the rodman, and one person to hold the zero end of the tape at the center line. When a hand level is used, two persons can do the job. The instrumentman uses the hand level and holds the zero end of the tape and is positioned at the center-line station as the rod reading is taken. The procedure is a trial and error process. Under field conditions, the rodman is at times as much as 200 or 300 feet away from the instrumentman. If power equipment is operating nearby or a wind is blowing, oral instructions cannot be given to the rodman about where to take trial shots. In other instances there may not be a clear view of the ground slope at the station being worked. Consequently, the rodman must know as much as the instrumentman does about the theory and practice of setting slope stakes. The speed and efficiency of the party depend on the rodman more than on any other member. The rodman must always be mentally alert. The most practical field procedure requires the rodman to know the value of W/2 and of s (the slope ratio). This is not difficult, since these values are usually constant for several stations, and the rodman can be informed when they change. A typical procedure for setting slope stakes is as follows:
1. The instrumentman computes the center-line cut or fill, using the HI, finished grade, and the existing ground elevation. Refer back to Figure 15-36.
2. The instrumentman calls or signals the center-line cut or fill to the rodman.
3. The rodman mentally computes the approximate value of d by multiplying h x s and adding W/2. The rodman pulls the tape taut while holding the tape at the computed distances.
4. Noting the approximate rise or fall of the ground, the rodman adjusts the approximate value of d, moves to the d point, and sets up the rod for a trial shot.
Figure 15-43 � Cut section.
5. The instrumentman quickly calculates the cut or fill at this point and calls the value to the rodman.
6. The rodman compares the information with the estimated cut or fill. The rodman should be fairly close and should know at once whether to move toward or away from the center line. Having a much shorter distance over which to estimate ground slope, the rodman again estimates new cut or fill and hs + W/2, and moves the rod to the new d value.
7. The instrumentman again gives the cut or fill; if the value checks, the rodman calls or signals back the cut or fill and the distance.
8. The instrumentman quickly checks the two values mentally, and if the values are correct, records the values in the field book, signaling �Good� to the rodman.
9. The rodman marks and drives the stake. With practice and on fairly smooth ground, a good rodman will seldom miss the first trial by more than 0.2 foot vertically and will, quite often, hit the correct value on the first trial. Figure 15-44 shows the application of these procedures to an actual situation. The following data is known for this slope-stake stakeout:
1. The station is 15 + 00.
2. The W/2 (from the typical design section) is 20 feet.
3. The slope ratio is 1:1; therefore, s = 1.
4. The existing ground elevation at the center line (from the previously run profile) is 364.00 feet.
5. The HI is determined to be 369.30 feet at that setup.
Figure 15-44 � Setting slope stakes.
The steps taken by the instrumentman and the rodman are as follows:
1. The instrumentman determines the center-line cut by subtracting 350.7 feet from 364.0 feet to get the cut, or 13.3 feet.
2. The rodman holds at the center line for a check. The rod should read 369.3 (the HI) minus 364.0, or 5.3 feet.
3. The instrumentman calls to the rodman, �Cut 13.3 feet.�
4. The rodman computes d= 20+(1 x 13.3) = 33.3 while walking to the left.
5. As the rodman approaches about 30.0 feet from the center line, he/she estimates that the ground has a fall of 4 feet, and therefore computes the new cut as 13.3 � 4.0, or 9.3 feet. This means a new d of 20 + (1 x 9.3) = 29.3 feet. 6. The rodman sets up the rod 29.3 feet from the center line, as measured by metallic tape. 7. The instrumentman reads 10.1 on the rod and computes the new cut as 369.3 � (350.7 + 10.1), or 8.5 feet. Note that the grade rod and ground rod values can be used here as explained earlier; the new cut then will be 18.6 � 10.1 = 8.5 feet. Refer back to Figure 15-36. 8. The instrumentman calls, �Cut 8.5,� to the rodman. 9. The rodman computes d = 20 + (1 x 8.5) = 28.5 feet. The rodman knows, therefore, that 29.3 feet from the center line is too far out. 10.Figuring that the ground rises about 0.1 foot between 29.3 left and 28.5 left, the rodman calculates that the more nearly correct cut will be 8.5 + 0.1, or 8.6 feet. 11.By using this cut, the rodman calculates the new d as 20 + (1 x 8.6), and sets the rod at 28.6 feet left. 12.The instrumentman reads and computes the new cut as 369.3 � (350.7 + 10.0) = 10.0 on the rod 8.6 feet. 13.The instrumentman calls, �Cut 8.6,� to the rodman. 14.The rodman sees that the actual cut of 8.6 feet agrees with his estimated cut of the same, and calls, �Cut 8.6 at 28.6,� to the instrumentman. 15.The instrumentman checks d = 20 + (1 x 8.6) = 28.6, signals the rodman, �Good,� and makes the following entry into the field book: 28 86 c 16.The rodman marks a stake with 15 + 00 and C86 and drives it in the ground at 28.6 feet left. More often, slope stakes may be set by using a hand level. The distances out are generally measured to the nearest half or tenth of a foot. If a slope stake is placed in an offset position, the offset distance is also marked on the stake so the equipment operator is not confused about its actual location. Slope stakes are seldom used in areas requiring less than 2 feet of cut or fill. 15-56
Generally curbs and gutters are usually constructed before the finish grading is done. The curb constructors acquire their line and grade from offset hubs like those described previously. Guided by the offset hubs, the earthmovers make the excavation for the curb, form-setters set the forms, and the concrete crew members pour, finish, and cure the curb. After the curb is constructed, shaping the sub-grade to the correct sub-grade elevation and laying the pavement to correct finished grade is simply a matter of measuring down the correct distance from a cord stretched from the top of one curb to the top of the opposite curb.
Pavement stakeout depends on the type of paving equipment used. The steps commonly used for paving concrete highways are as follows: 1. Set a double line of steel side forms, equipped with flanges that serve as tracts for traveling paving equipment. 2. Fill the space between the forms with concrete poured from a concrete paving machine (commonly called a paver). 3. Spread the concrete with a mechanical spreader that travels on the flanges of the side forms. 4. Finish the surface with a finisher, a machine that also travels on the side forms. The line-and-grade or layout/stakeout problem consists principally of setting the side forms in line with the upper edges of the flanges for the prescribed highway grade. If the finished grade shown on the plans is the center-line grade, then the forms are set with tops at the center-line grade less the crossfall. If the design elevations are shown for points other than those on the center line, the form elevation is related to the design points as indicated by the typical section. Concrete paving is also done by the slip form method, which uses a sliding or traveling section of formwork to spread and finish the concrete. The machinery is kept on line and the pavement is finished at grade by a control device or devices. The line control device usually follows a wire stretched between rods offset from the pavement edge. Forms are not usually used in asphalt paving. Asphalt paving equipment, in general, is designed to lay the pavement at a given thickness, following the fine-graded sub-grade surface.
A structural survey is part of the chain of human activities that brings a structure such as a building, a bridge, or a pier into existence.
The first major step in highway construction is usually the rough grading or earthmoving which brings the surface up to, or down to, the approximate elevation specified for the rough grade. The stakeout for rough grading is commonly done by the grid method. The area to be graded and the prescribed finish grade elevation on the site or plot plan are laid off in 25-, 50-, or 100-foot grid squares. The elevation at each corner point is determined by the following process: 15-57
The next major step after the rough grading is completed is the building stakeout. Building stakeout involves locating and staking the main horizontal control points of a building. These are usually the principal corner points plus any other points of intersection between building lines.
Figure 15-45 shows a simple building stakeout. The site plan shows a 40 x 20-foot rectangular structure, with one of the long sides parallel to, and 35 feet away from, a base line. The base line is indicated at the site and on the plans by Monuments A and B.
Figure 15-45 � Building stakeout.
One of the short sides of the building lies on a line running from C, a point on AB 15 feet from A, perpendicular to AB. The other short side lies on a similar line running from D, a point on AB 40 feet from C and therefore 40 + 15, or 55 feet from A, perpendicular to AB.
The steps in the stakeout procedure are as follows:
The accuracy of a rectangular stakeout can be check by measuring the diagonals of the rectangle.
The diagonals should be equal. The correct length of each diagonal can be checked by applying the Pythagorean Theorem, as shown in Figure 15-45.
For a large rectangle, checking the accuracy of the stakeout by angular measurement with the transit may be more convenient. For example: Determine the correct size of angle GEH in Figure 15-45 by a convenient right-triangle solution, such as
tan a = 20 = 0.50000 40
The angle with tangent 0.50000 measures (to the nearest minute) 26�34�. Therefore, angle FEH should measure
90� 00� � 26� 34�, or 63�26�
The corresponding angles at the other three corners should have the same dimensions. If the sizes as actually measured vary at any corner, the stakeout is inaccurate.
Batter boards are marks placed for use as references or guides during the initial excavation and rough grading of building and/or a sewer line construction. Batter boards are temporary devices used to support stretched cords that mark the outline and grade of the structure.
Batter boards consist of 2 x 4- inch stakes driven into the ground. Each stake has a crosspiece of 1 x 6-inch lumber nailed to it. The stakes are driven approximately 3 to 4 feet away from the building line where they will not be disturbed by the construction. They are driven far enough apart to straddle the line to be marked. Note in Figure 15- 46, only three stakes are driven on outside corners because one is a common post for two directions. The length of the stakes is determined by the required grade line. They must be long enough to accept the 1 x 6-inch crosspiece to mark the grade.
Figure 15-46 � Batter boards.
The 1 x 6-inch crosspiece is cut long enough to join both stakes and is nailed firmly to them after the grade has been established. The top of the crosspiece becomes the mark from which the grade will be measured. All batter boards for one structure are set to the same grade or level line. A transit is used to locate the building lines and to mark them on the top edge of the crosspiece. A nail is driven at each of these marked points, or a V notch is carved at the top outer edge of the crosspiece towards the marked point and the nail is driven on the outer face of the board.
When a string is stretched over the top edge of the two batter boards and is held against the nails or against the bottom of the notch, the string defines the outside building line and grade elevation.
Batter boards are set and marked as follows:
Utilities is a general term applied to pipelines such as sewer, water, gas, and oil pipelines, and communications lines such as telephone or telegraph lines and electric power lines.
For an above-ground utility, such as a pole-mounted telephone or power line, the survey problem consists of locating the line horizontally and marking the stations where poles or towers are to be erected. Often, the directions of guys and anchors maybe staked. Occasionally, pole height for vertical clearance of obstructions is determined.
For an underground utility, often both line and grade must be determined. For pressure lines, such as water lines, it is usually necessary to stake out only the line, since the only grade requirement is that the prescribed depth of soil cover be maintained. However, staking elevations may be necessary for any pressure lines being installed in an area that is to be graded downward or has conflicting underground utilities.
Gravity flow lines, such as storm sewer lines, require staking for grade to be sure the pipe is installed at the design elevation and gradient (slope) needed for gravity flow through the pipe.
Grade for an underground sewer pipe is given in terms of the elevation of the invert. The invert of the pipe is the elevation of the lowest part of the inner surface of the pipe. Figure 15-47 illustrates a common method of staking out an underground pipe.
Figure 15-47 � Use of batter boards (with battens) for utility stakeout.
Both alignment and elevation are facilitated by a line of batter boards and battens (small pieces of wood) set at about 25- to 50-foot intervals. The battens, nailed to the batter boards, determine the horizontal alignment of the pipe when placed vertically on the same side of the batter boards and with the same edges directly over the center line of the pipe. The alignment of the battens must be checked as work progresses. Use a sighting cord, stretched parallel to the center line of the pipe at a uniform distance above the invert grade, to transfer line and grade into the trench. The center line of the pipe should be directly below the cord, and the sewer invert grade should be at the selected distance below the cord. A measuring stick, also called a grade pole, is used to transfer the grade from the sighting cord to the pipe, as shown in Figure 15-47. The grade pole, with markings of feet and inches, is placed on the invert of the pipe and held plumbed. The pipe is then lowered into the trench until the mark on the grade pole is on a horizontal line with the cord.
Figure 15-48 shows another method of staking out an underground sewer pipe without the use of battens. Nails are driven directly into the tops of the batter boards so a string stretched tightly between them defines the pipe center line. The string or cord can be kept taut by wrapping it around the nails and hanging a weight on each end. Similarly, the string (or cord) gives both line and grade.
Figure 15-48 � Batter boards (without battens) for utility stakeout.
A finished structure seldom matches to the original plans in every detail. Unforeseeable difficulties often make variations from the plans necessary.
The purpose of an as-built survey is to record the variations. The as-built survey begins as soon as it becomes feasible. This means the actual horizontal and vertical locations of features in the completed structure should be determined as soon as the features are erected.
At times, variations from the original plans are recorded on new tracings of the working drawings. When differences are identified, the as-built data is recorded in the place of the original design data. Sometimes, reproductions of the original drawings are used with variations recorded by crossing out the original design data and writing in the as-built data.
In either case, the term �as-built survey,� together with the date of revision, is written in or near the title block.
Warning
|
Where blasting or logging is going on, inform the powder crew or logging crew of the location of the area where surveyors are working. Also, instruct the individual crew members of the survey party to be alert at all times�particularly listening for the warning signal given by a crew using powder to set off a charge or a logger felling a tree.
When surveying near highways, railroads, or airstrips, use red flagging generously. Do not use flagging in a combat area, however. Place flagging on the legs of the surveying equipment and at a few places along the measuring tape. Put flags on rods and range poles. Attach flagging to hats and to the back of shirts or jackets.
Constantly think of personal safety when working near heavy construction equipment. Inform equipment operators when surveyors are in the vicinity. Alert the surveying crew that an equipment operator's vision is often obscured by dust or by the equipment itself. Do not climb directly behind another crew member when ascending steep, rocky slopes. If the crew member were to fall, loosen a rock, or drop something, serious injury could result to the crew below.
Warning
|
To avoid slides or cave-ins, support the sides of the excavations 5 feet or more deep by substantial bracing, shoring, or sheet piling if the sides are steeper than the angle of repose. The angle of repose is the maximum angle at which material will repose without sliding. Trenches in partly saturated or otherwise highly unstable soil should be stabilized with vertical sheet piling or suitable braces. Shore, brace, or underpin foundations of structures adjacent to excavations as long as the excavation remains open. Do not allow excavated or other material to accumulate closer than 2 feet from the edge of an excavation. In a traffic area use barricades, safety signs, danger signals, red lights, or red flagging on at least two sides.
Walk at least 2 feet away from the edge of a vertical excavation. Near thoroughfares or walkways, excavations should have temporary guardrails or barricades and if permissible, depending on combat conditions, red lights or torches should be illuminated from sunset to sunrise.
Do not enter a manhole until certain it is free from dangerous gases. Do not guess. Wait for clearance from a competent authority if there is any question as to whether a sewer is free of gas. Do not smoke in manholes. If illumination is required, use a safety flashlight or lantern.
Avoid contact with all electric wiring. Never throw a metal tape across electric wires. Use breaking chain if crossing wiring is required. Avoid placing your body over wiring to reduce the likelihood of falling onto dangerous wiring.
Before climbing a tree, ensure it is safe to climb, and carefully check the condition of the branches that you might use for standing. Different kinds of wood vary greatly in strength. Oak, hickory, and elm trees are strong, flexible wood safe for climbing. Limbs of all trees become brittle at low temperature, and have a tendency to break easier in cold weather. Dead branches or those containing many knots or fungus are weaker.
When standing on a limb, place your feet as close to the parent trunk as possible. Climb with care when limbs are wet or icy. To prevent an eye injury, wear goggles when working in bushy trees.
Warning
|
When cutting tools are required to clear a working space in a tree, raise and lower them with a hand line. Never throw tools up into a tree or down onto the ground.
When a structure has an access opening and is below the street, such as a manhole or a transformer vault, it should be protected by a barrier or other suitable guard when the cover to the access opening is removed.
Make certain ice will support your weight before crossing. The thickness and the nature of ice are important in determining its carrying capacity.
Because part of the supporting power of ice is derived from the water below it, a layer of ice that is in contact with the water surface is safer than one that has no contact with the water surface.
An ice layer usually becomes thinner over current, near banks of streams or lakes, over warm springs, and over swampy ground. "Rotten ice" us identifiable by its dull color and a honeycomb texture that has little supporting power.
| Test Your Knowledge 16. Fieldwork on the construction of a road being built on a 5-year-old airport would very likely begin with what type of survey?
17. Direct air observation of an area to be reconnoitered offers what main advantage?
18. Which of the following tasks in constructing a highway is part of the preliminary survey?
19. Which of the following details must be shown on a plan view of a proposed highway?
20. On the cross-section paper most widely used in surveying offices, the horizontal lines are spaced how far apart?
21. The batter boards should be placed how many feet from the building lines so as not to interfere with construction?
22. Red flagging should be used on the legs of your instrument when you are surveying in the vicinity of which of the following areas?
|
This lesson addressed the leveling operations used to determine elevations of points or the differences in elevation between points on the earth�s surface. The data gathered from leveling operations is used for engineering designs, mapping, and construction projects. This lesson discussed the basic principles of and the methods used in direct leveling. The duties and responsibilities of the leveling crew were also addressed. Finally, the lesson included a general description of basic engineering surveys and the various construction-site hazards commonly associated with conducting a survey.
1. To be used as elevation references in the development or expansion of a permanent naval station, you should establish monument BMs in which of the following locations?
2. Mean sea level (MSL) differs from mean tide level (MTL) in what way?
3. The correct way to obtain the MSL value for a month�s tide tabulated record is to add all daily sums for the month and to divide this total by the sum of what specific units of time in that month?
4. Assume you are engaged in a hydrographic survey of the water approaches to Naval Air Station, Adak, Alaska. Your soundings should refer to what datum?
5. The proper way to remove an engineer�s level from its carrying case is to grasp it firmly by what part(s)?
6. You are setting up an engineer�s level on a concrete surface. You mount the instrument on a tripod placed inside a floor triangle. This precaution will protect the tripod from which of the following accidents?
7. The whole foot numbers on a Philadelphia rod are what color?
8. In leveling, which of the following statements best defines height of instrument (HI)?
9. By using the technique of balancing shots, you can eliminate which of the following effect(s) in differential leveling?
10. In profile leveling, rod readings taken from points that are neither BMs nor TPs are entered under what heading in the field notebook?
11. You are doing cross-section leveling for a highway road survey. The profile center-line elevation at station 25 + 00 is 112.5 feet and eye height is 5.3 feet. On a rod held 20 feet from the center line you read 11.2 feet. What is the elevation, in feet, at this point?
12. In third-order leveling, the starting and closing BMs must be of which of the following orders accuracy?
13. What is the first step in a reconnaissance survey?
14. A field reconnaissance party follows the route previously marked on a map to verify actual conditions on the ground. Which of the following conditions, relative to an engineering study, should be noted?
15. Your survey party is assigned the task of completing a reconnaissance survey of a 3-mile road in hilly, wooded terrain. For this survey, your party should carry which of the following equipment?
16. As the lead surveyor laying out the final location of a roadway center line, you suspect that the preliminary survey was in error regarding the exact location of the center line. Which of the following actions should you take?
17. After the surface elevations have been plotted on the cross-section paper, the points should be connected in which of the following ways?
18. In the plotting of cross sections, the vertical scale relates to the horizontal scale in which of the following manners?
19. During what stage of a road construction project are �blue tops� used?
20. What term is used for the natural earth surface below the pavement of a highway?
21. In curb construction, construction crews should obtain line and grade from which of the following sources?
22. Pavement stakeout is primarily dependent upon which of the following factors?
23. The invert elevation of an underground sewer pipe is taken at what point on the pipe?
24. For any construction project, what is the optimum time for the as-built survey to begin?
25. Which of the following actions should you take when you are running a tapetransit traverse that crosses electric wires?
26. Excavations that are what minimum depth, in feet, must be suitably braced and shored to prevent cave-ins?