TEXT ASSIGNMENT: Attached Memorandum
LESSON OBJECTIVES
Upon completion of this lesson on Bills of Materials, you should be able to accomplish the following in the indicated topic areas:
1. Terminology. Define the term "bill of materials."
2. Organization of Bills of Materials. Describe the organization of a bill of materials.
3. Reading Bills of Materials. Read a bill of materials for a construction project to determine quantities needed for each type of material.
ATTACHED MEMORANDUM
A bill of materials is a grouped compilation based on takeoffs and estimates of all materials needed to complete a structure. The bill of materials for a given project is organized into a tabulated statement to include item number (parts and materials), name, description, unit of measure, quantity and, where called for, the stock size and number, and sometimes the weight. You may be familiar with bills of materials by some other designation such as "materials takeoff sheets" or "materials estimate sheets."
5-2. COMPILATION
Bills of materials are usually made up by the draftsman at the time of preparation of the original drawings; you simply utilize them when ordering materials. However, where no bills of materials accompany field prints they must be compiled by the constructing or erecting forces; thus, you should understand and be able to work with or develop bills of materials. Reasonable accuracy can best be obtained by having separate bills of materials prepared by at least two estimators. They can then be compared and one copy corrected or both consolidated into a final bill of materials.
a. Takeoff and Estimate. The takeoff usually is an actual tally and checkoff of the items shown, noted, or specified on the construction drawings and specifications. The estimated quantities are those known to be necessary but which may not have been placed on the drawings, such as nails, cement, concrete-form lumber and tie wire, temporary bracing or scaffold lumber, etc. These are calculated from a knowledge of construction methods that will be used for field erection. You can use the information given in appendix B to help in making up an estimate.
b. Plans. Both architectural and engineering plans provide the means by which names of the various items can be listed in order to make up the bills of materials. Indicated or scaled dimensions of buildings or utilities layouts are used to determine material unit dimensions.
c. Quantities. Quantities are usually taken from the plans by extracting and listing one type of material at a time followed by a regrouping of those types by sizes commencing with the smallest and progressing to the largest.
d. Tabulation. The tabulation should include column headings for each item as follows:
(1) Item number. Number of the item in each section.
(2) Section number. The number assigned to the appropriate major groups such as: general construction, electrical, plumbing, etc.
(3) Item name.
(4) Unit of measure.
(5) Quantity.
5-3. EXAMPLE BILL OF MATERIALS
a. Figure 5-1 shows the floor pan and detail drawings for a 50-man barracks on a concrete floor. This set of construction drawings should be sufficient to develop a bill of materials.


Figure 5-1. Construction drawing for 50-man barracks.
b. Figure 5-2 is the bill of materials for the 50-man barracks. It contains a great deal of information. To develop a detailed bill of materials such as this would require experience in construction print reading, construction procedures, and methods of estimating quantities.
Figure 5-2. Bill of materials for 50-man barracks.
5-4. READING PREPARED BILL OF MATERIALS
As stated previously, the bill of materials is usually made up by the draftsman at the time of preparation of the original drawings. It is important that you be able to read a prepared bill of materials.
a. Heading. The headings were discussed above. Under quantities required in figure 5-2, the types of wall panels are: (1) WPW-window panel, (2) DPW-door panel, and (3) BPW-blank panel. The final W after all the abbreviations indicates that wood cladding and felt are to be used to cover the structure.
b. Body. In the body, each of the major groups (frame, cladding, floor, etc.) have been listed separately. Each major group has been subdivided into groups of common items and under the subgroups the individual items have been listed and described in detail. For example, the major group, FRAME, has been divided into the subgroups, lumber and nails. Then, under lumber, each size board that is needed is listed and described. The units of measure for each item are abbreviated. You should be familiar with these abbreviations. The amounts listed under quantities required are those required for the total structure. Figure 5-3 is the construction drawing for a frame for an officer's tent. Figure 5-4 is a completed bill of materials for figure 5-3.
Figure 5-3. Construction drawing for frame for officer's tent.
Figure 5-4. Bill of materials for frame for officer's tent.